Create Visit Package – A summary of the activity

Using the “Central Planning” business component, the central planner creates the visit package for scheduled maintenance. This activity allows you to create a visit package for unscheduled maintenance.

The visit package is an aggregation of all the maintenance activities that needs to be accomplished during the visit of an aircraft to the maintenance execution facility. Besides forming the means for pre-execution planning of a visit, it also acts as the control unit for monitoring the various activities during the course of execution. The visit package is assigned to a primary work center, which acts as the primary responsibility center for the check execution.

A visit package is created on an aircraft and is assigned a unique number generated by the system. Planning information such as the expected grounding date, planned start and end dates and the execution priority is also identified. A visit package typically comprises of maintenance activities that are to be accomplished during the aircraft visit. These include:

It also has the material and resource requirements for execution of the above activities

While the central planner on the respective execution centers creates planned visit packages, unscheduled visits can be planned and executed locally (at the execution center). In such events, the visit planner can optionally include any upcoming planned maintenance activity (as forecasted by the aircraft’s maintenance planner) or deferred maintenance activities, if any.

The activity list is then exported to the project management software where the inter-dependencies between the tasks are established and the resource constraints evaluated, to arrive at the schedule dates. The revised schedules are then updated back into the visit package.

Top

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Getting familiar with the pages inside

Go to page…

For…

Create Visit Package

Creating a visit package for unscheduled maintenance

Edit Resource Requirements

Entering resource requirement for a work unit

Edit Material Requirements

Entering material requirement for a work unit

Process Deferred Discrepancies

Processing deferred discrepancies

Select Work Units for Opportunity Maintenance

Selecting work units for performing opportunity maintenance in a visit package of type “unplanned”

Plan Visit Package

Planning visit package information

Edit Work Content

Modifying work scope details

Update Component Removal List

Entering component removal details

Edit Visit Package Details

Modifying visit package information

Edit Visit Level Material Requirements

Entering material requirement for visit package

Edit Visit Level Resource Requirements

Entering resource requirement for visit package

Top

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

What you can do in this activity

Process discrepancy

Specify the component restoration details

Export/Import visit package to/from project management tools

Modify work scope details

Define resource and part requirements at the work unit level or at the visit package level

Create deferment request

Specify deferral limits for a work unit

View other visit packages associated to the work center

Top

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Process discrepancy

Discrepancies are typically the symptoms of the problem, which are observed by the person-in-charge, like pilot, mechanic or the cabin crew, and it is usually recorded in the flight log or hangar work order . A maintenance report is created, in the “Discrepancy Processing” business component, to process the discrepancies. Sometimes, due to reasons such as non-availability of spares or ill-equipped maintenance station, the maintenance report may be deferred. The confirmed deferred maintenance reports that are not processed for the aircraft can be processed in this activity.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Specify the component restoration details

You can specify the component that has to be removed or replaced in the aircraft while performing the maintenance activity. You can also specify the work unit that has to be performed for the restoration of the component.

Note: The system retrieves the specified work unit from “Component Maintenance Program” business component

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Export/Import visit package to/from project management tools

You can define the visit package details and export the work unit details to the project management software. The software will calculate the scheduled start date and end date automatically for the work units included in the visit package. You can also import the visit package contents from the project management software.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Modify work scope details

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Define resource and part requirements at the work unit level or at the visit package level

You can select a work unit and modify the parts and the resources required for executing the work unit.

You can specify the parts and the resources which are over and above the requirements of individual tasks.

You can view the consolidated material and resource requirement and modify resource and the part details.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Create deferment request

You can defer work units allocated to the visit package by the central planner. You may have to defer a work unit due to various reasons such as resource constraints, flying schedules of an aircraft or workload of an execution center. Each deferment should be accompanied by an appropriate reason for deferring, and requires approval from an authorized person.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Specify deferral limits for a work unit

You can specify the deferral limits for a work unit. You can specify time based and usage based deferral limits. The work unit will be deferred based on the deferral limits specified here.

The system displays the “Create Deferment Request” page.

The system displays the “Edit Deferral Limits” page.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

View other visit packages associated to the work center