Entering maintenance object and quotation details
Using this tab you can update the maintenance object and quotation details.
Select the “Maint. Object & Quotation Details” tab in the "Record Quotes" page.
The system displays the following in the “Maint. Object Details” multiline:
Line# |
The number identifying the line in the repair order |
Part # |
The number identifying the part for repair. |
Mfr. Part # |
The number provided by the manufacturer of the part. |
|
|
Repair Cost |
The cost of repairing the part. Note: This field is mandatory, if
However, do not enter any value, if
|
Exchange Cost |
The exchange cost for the part sent for repair with reference to a PBH/PBH-Exchange purchase order. Note: This field is mandatory, if RO type is ‘Exchange’. However, you must not specify any exchange cost, if RO type is ‘Normal’. |
BER Quantity |
Qty which are declared as “Beyond Economic Repair” |
Note:
|
|
BER Cost |
The cost incurred in evaluating component, (Decimal). |
Note: You must state the BER cost if you have specified the BER quantity. |
|
Salvage Action |
The place where the component that has been declared as BER is to be salvaged. Use the drop-down list box to specify the action, which could be “By Repair Shop” or “By Operator”. |
|
|
|
|
Note: You must select a salvage action, if the BER quantity is greater than Zero. Alternatively, if you do not select any salvage action, the BER quantity must be Zero.
Salvage Value / Unit |
The estimated scrap value of the component/part (Numeric, 28). |
|
|
The system displays the following in the multiline: |
|
Part Description |
The name / description of the part. |
Part Type |
The type of the part, such as “Raw Material”, “Component”, “Expendable”, “Tool”, “Miscellaneous”, “Consumables” and “Kit”. |
Facility Object # |
The identification number of the facility object related to the part. |
Facility Type |
The type of the facility object, such as Tool, Equipment or Other relate to the part. |
Quantity |
The number of parts for repair. |
UOM |
The unit of measurement applicable for the part. |
Serial # |
The serial number of the part. |
Lot # |
The lot number of the part. |
Stock Status |
The user-defined stock status of the part. |
Line Status |
The status of the line in the repair order. |
Enter the following in the multiline.
Remarks |
Additional information on the component or part. Select the icon to view the remarks history. |
Enter the following in the “Quotation Details” group box:
Quotation Ref # |
A unique reference number identifying the quotation, (Alphanumeric, 40). |
Quotation Type |
Use the drop-down list box to select the types of quotation, which could be “Firm” or “Estimate”. The system displays “Firm” by default. |
Quotation Date |
The date on which the quotation is received by the repair shop. Ensure that the quotation date is greater than or equal to the date on which the “Acknowledgment” was received. This date should be lesser than or equal to the current date. |
Price Held Firm Time |
The validity time frame given by the repair shop for the quotation. Use the drop-down list box to specify the time held, which could be “Days”, “Weeks” or “Months”. The system displays “Days” by default. |
Note: The system allows you to amend the repair order only during the duration specified in the Price Held Firm Time field ensuing the Quotation Date. For example, with a Quotation Date of April 5th and a Price Held Firm Time of four days, the date on which you amend the repair order must lie between April 5th and April 9th. |
|
Currency |
Use the drop-down list box to select the currency of the quotation, which could be the base currency or any other currency in “Active” status, which has a conversion factor set for the base currency. However, if the repair shop is being created for a group company, the base currency must be valid or the exchange rate for conversion to base currency must be available in the group company. |
Note: If no currency is selected, the system considers the “Active” currency mapped to the supplier in the “Add Location Details” activity of the “Supplier” business component.
The system displays the following:
Exchange Rate |
The exchange rate of the currency, with respect to the base currency. |
Enter the following:
Component List Price |
The list price of the component (Decimal). |
Exchange Fee |
The exchange fee charged by the repair shop for an exchange repair order (Decimal). |
Est. Man Hrs. |
The total man hours estimated to complete the repair order (Decimal). Ensure that the value, if entered, is positive. |
Cost / Man Hr. |
The cost per person spent in hours (Decimal). It is mandatory to enter this cost if the estimated man-hours are specified. |
Labour Cost |
The cost of labour that will be incurred on the repair order (Decimal). |
The system displays the following:
Total Labor Cost |
The total estimated labour cost that will be incurred on the repair order. |
Enter the following:
Material Cost |
The cost of material that will be incurred on the repair order (Decimal). This cost is calculated by multiplying the rate defined for the material with the quantity of parts estimated. |
The system displays the following:
Total Material Cost |
The total estimated material cost that will be incurred on the repair order, inclusive of taxes, charges and discounts. |
Enter the following:
Misc. Cost |
Any extra cost that will be incurred on the repair order (Decimal). Ensure that the value, if entered, is positive. |
Total Repair Cost |
The total estimated repair cost that will be incurred (Decimal). |
The system displays the following:
Total Cost |
The total estimated cost that will be incurred on the repair order. Total Cost = Total Repair Cost + Exchange Cost + Document TCD Value |
Basic Currency Value |
The value of repair order in base currency. Convert the total cost from currency specified to cost in base currency, using the exchange rate between the base currency as currency specified. |
Enter the following:
Remarks |
Any additional comments, pertaining to the quotation given by the repair shop, (Alphanumeric, 255). |
Quotation Comments |
Any additional information on quotation. Note: This field is mandatory, if you intend to select the “Override BER Limit” check box. |
To proceed carry out the following:
Click the "Supplier, Part & Warranty Details" tab.