Maintenance Cost Report – A summary of the activity

In this activity, you can generate the maintenance cost report for the maintenance activities performed on the aircraft. The line maintenance department executes scheduled and unscheduled jobs on aircrafts every day. The maintenance cost for the scheduled and unscheduled jobs performed on the aircraft will be computed. Maintenance cost is the cost of labour / material / facilities directly expended in performing maintenance on an aircraft. This report is generated based on parameters such as aircraft registration number, work center number, technical log number, work unit number, from and to date, and display option.

Maintenance Cost Report will provide the following information:

4      Estimated and actual maintenance cost expended on scheduled maintenance jobs.

4      Actual maintenance cost  for unscheduled jobs performed and recorded in Technical Log.

The maintenance cost computation will be based on the estimation available in the task master and the actual consumption reported in the technical log. Technical Log is a document carried on an aircraft, which contains the aircraft maintenance record. Only the technical logs that are in “Confirmed” status will be considered for cost computations.

Maintenance Cost Report

Report Heading

Maintenance Cost Report

Header Information

Report Criteria

Aircraft Reg #, Work Center #, Technical Log #, Work Unit #, From Date, To Date, Display Option.

Columns Printed

Maintenance Cost Details

a.       Group Header Details

           Aircraft Reg #, Work Center #

b.       Tech. Log #

c.       Work Unit

d.       Planned Maintenance

Est. Mat. Cost, Act. Mat. Cost, Est. Res. Cost, Act. Res. Cost

e.       Unplanned Maintenance

       Act. Mat. Cost, Act. Res. Cost, Misc Cost

Footer Information

Generated On

Click here to know more on "Generate Maintenance Cost Report".