Setting discrete production parameters
This page allows you to set the BU level parameters for the “Discrete Production” business process chain. You can the process parameters as well as the functional default values. The system saves the parameters and also updates the login ID of the user and the system date along.
Select the “Set Parameters – Discrete Production” link from the “Business Unit Parameter Setup” business component.
The “Set Parameters – Discrete Production” page appears.
Enter the following fields in the “Process Parameters” group box:
Deploy Order Status (Accepted) |
Use the drop-down list box to specify whether the work orders in “Accepted” status is deployed. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Deploy Order Status (Firm) |
Use the drop-down list box to specify whether the work orders in “Firmed” status is deployed. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Stock Transfer based on Bill of Distribution |
Use the drop-down list box to specify whether the bill of distribution properties affects the implementation of manual stock transfer. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Auto Authorize Stock Transfer on Release |
Use the drop-down list box to specify whether the released stock transfer orders are authorized by the system automatically. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Note: If “No” is selected in this field then the released stock transfer orders must be authorized manually.
Option Rule Engine based on |
Use the drop-down list box to specify the selection of position variants with respect to a work order. You can select from “Start Date” or “Due Date”. |
|
|
|
|
The system displays “Due Date” by default on launch of the page. |
|
Action Message Set Up Level |
Use the drop-down list box to select the level at which the different types of action messages are generated during the Material Requests Planning process. You can select from “Business Unit” or “Plant”. |
|
|
|
|
The system displays “Business Unit” by default on launch of the page. |
|
Allow multiple Planning Groups for an Item |
Use the drop-down list box to specify whether the same item can be included in multiple planning groups. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Plant/warehouse mandatory in Analyse Item Plan |
Use the drop-down list box to specify whether the Plant and Warehouse details must be entered compulsorily in the “Analyze Item Plan” activity of the “Supply Chain Planning” business component. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Min/Max Order qty to be multiples of Order step |
Use the drop-down list box to specify whether the Min and Max quantities in Lot size specification must be multiples of the step value specified. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Note: If “Yes” has been selected in this field and if the Step value has been entered as 8, then the valid Min and Max values would be 16 and 88 respectively.
On the other hand, if “No” has been selected in this field and if the Step value has been entered as 8, then the following Min and Max values are also considered to be valid.
Min = 9 and Max = 99.
Check user permission in Mass change WO Update |
Use the drop-down list box to specify whether users with “Production Controller” permissions are alone permitted to perform Mass Change, that is, replacement of materials during work order updation. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Ignore Lot sizing for Manual Orders |
Use the drop-down list box to specify whether lot sizes are considered for manual orders. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
EC to impact Production Bill |
Use the drop-down list box to specify whether the engineering changes will be included in the production bills. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
EC to impact Costing Bill |
Use the drop-down list box to specify whether the engineering changes will be included in the costing bills. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
EC to impact Engineering Bill |
Use the drop-down list box to specify whether the engineering changes will be included in the engineering bills. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
EC to impact Sub-contract Bill |
Use the drop-down list box to specify whether the engineering changes will be included in the sub-contract bills. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
PR generation options by MRP |
Use the drop-down list box to specify the options for the generation of purchase requests in a Planning run. You can select from “Purchase Suggestion”, “Unauthorized PR” or “Authorized PR”. |
|
|
|
|
|
|
The system displays “Purchase Suggestion” by default on launch of the page. |
|
SCR generation options by MRP |
Use the drop-down list box to specify the options for the generation of subcontract requests in a Planning run. You can select from “SC Suggestion”, “Unauthorized SCR” or “Authorized SCR”. |
|
|
|
|
|
|
The system displays “SC Suggestion” by default on launch of the page. |
|
Serial No Assigned for Consumption |
Use the drop-down list box to specify the method of assigning serial numbers from the item inputs consumed to the outputs produced. You can select from “Manual” or “Automatic”. |
|
|
|
|
|
The system displays “Manual” by default on launch of the page. |
Auto Generation of PS NO |
Use the drop-down list box to specify whether the product structure number is generated automatically during creation. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Allow Duplicate PS Usage |
Use the drop-down list box to specify whether multiple product structure numbers with the same usage for an item can be present. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Auto generation of Mass change Ref (PS) |
Use the drop-down list box to specify whether the Mass change Reference number for product structure is generated automatically during creation. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Auto generation of Activity code |
Use the drop-down list box to specify whether the activity code is generated automatically during creation. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Auto generation of PP NO |
Use the drop-down list box to specify whether the process plan number is generated automatically during creation. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Allow Duplicate PP Usage |
Use the drop-down list box to specify whether the same process plan usage can be used across process plan numbers. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Auto generation of Mass change Ref (PP) |
Use the drop-down list box to specify whether the Mass change Reference number for process plan is generated automatically during creation. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Exclude Inactive PS in Cost Rollup |
Use the drop-down list box to specify whether the items in “Inactive” status must be considered during the process of Cost Rollup. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
Enter the following fields in the “Function Defaults” group box:
Default MPS Period |
Use the drop-down list box to select the time buckets / intervals for Master Production Schedule planning. You can select from “Day”, “Week” or “Month”. The system displays “Day” by default on launch of the page. |
MPS Planning Horizon (Days) |
The interval of Master Production Schedule planning in number of days (Integer). Mandatory. The value entered here must be greater than zero. |
MPS order no scheme |
Use the drop-down list box to select the numbering scheme for Master Production Schedule orders. All the numbering types that have been defined for the “Work Order” transactions will be available for selection. The system displays the default numbering type on launch of the page. |
Default MRP Release Periods |
The time period after which orders must be released for Material Request Planning (Integer). The value entered here must be greater than zero. |
MRP Horizon (Days) |
The interval of Material Request Planning in number of days (Integer). Mandatory. The value entered here must be less than or equal to the value entered in the “MPS Horizon (Days)” field. |
Unit Of Measure for Hours |
The representation of hours in the “Usage” business component (Alphanumeric, 128). Mandatory. The value entered here must have been defined in the “UOM Admin” business component. |
Default Cost Element for Labor |
Use the drop-down list box to specify the labor cost element that links the cost center and the resource type called “Labor”. All the “Activity” cost elements that have been mapped to the cost center and which are in “Active” status will be available for selection. |
Click the “Set” pushbutton to set the parameters.
The system saves the BU level process parameters and the functional default values. The system also updates the login ID of the user and the system date along.