This tab provides an overview of the estimation details of the task within the work order. You can also confirm the part / resource estimates.

Work Scope Items

Select this radio button to display all the tasks that have WBS code for which the process parameter ‘Workscoping Element’ is set as “Yes” in the “Set Process Parameters” page of the “Common Master” business component.

Detailed Items

Select this radio button to display all the tasks that have WBS code for which the process parameter ‘Execution Operations?’ is set as “Yes” in the “Set Process Parameters” page of the “Common Master” business component.

This radio button appears checked, by default.

The system displays the following fields in the “Task Summary Details” multiline:

#

The sequence in which the task must be executed in the shop work order.

Task #

The unique code identifying the task.

Task Description

The textual description of the task.

Estimation Status

The estimation status of the task, which could be “Pending Estimates”, “Pending Confirmation”, “Confirmed Estimates”, “Not Required”, “Pending Re-estimates” or “Released Estimates”.

Note that the system retrieves the cancelled tasks in the multiline if the task is cancelled when the Estimation Status is “Pending Confirmation / Released Estimates”

Est. Reqd. for

Indicates whether estimation is required for parts, resources or specific part. The system displays the following values:

  • Mtl. Est – Indicates that estimation is required for the parts.

  • Res. And Mtl. Est – Indicates that estimation is required for both parts and resources.

  • Specific Part – Indicates that estimation is required for a specific part.

Parts Estimated?

Indicates whether part estimates are available for the task. The system displays the values “Yes” or “No”.

Resource Estimated?

Indicates whether resource estimates are available for the task. The system displays the values “Yes” or “No”.

Est. Reqd.?

Indicates whether part / resource estimation is required for external work orders. The system displays the values “Yes” or “No”.

Warranty Reco.?

Use the drop-down list box to specify whether warranty is recommended for the part.  The system lists the options “Yes” and “No”.

  • If Warranty Resolution for the work order is set as “Accepted”, ‘Warranty Reco.?’ must be selected as “Yes” for the tasks.

  • If Warranty Resolution for the work order is set as “Rejected”, ‘Warranty Reco.?’ must be selected as “No” for the tasks.

  • If Warranty Resolution for the work order is set as “Partial”, ‘Warranty Reco.?’ must be selected as “Yes” for at least one task in the multiline.

Estimation Remarks

Any comments related to the part / resource estimation. Mandatory.

File Name

The name of the file which contains the task details.

Help facility available.

The system displays the following fields:

Exec. Status

The execution status of the task, which could be “Draft”, “Fresh”, “Planned”, “In-Progress”, “Completed”, “Pre-closed” or “Closed”.

Parent Task #

The code identifying the parent task.

Parent Task Desc.

The textual description of the parent task.

Root Task #

The code identifying the root task.

Root Task Desc.

The textual description of the root task.

Re-estimation Remarks

Any remarks related to the re-estimation of the part / resource. For external work orders, the system retrieves the remarks from the “Sale Quotation” business component.

Change Status to

Use the drop-down list box to change the status of the task. The system lists the value “Not Required”.

You can select the value “Not Required”, only if the Estimation Status of the task is "Pending Estimates" or "Pending Confirmation".

The system leaves the field blank, by default.

User Status

The user status with respect to the work order. The system lists all the 'Active' Quick Codes created for the Quick Code type 'User status' in the “Maintain Quick Codes” activity of the “Shop Work Order” business component.

The system leaves the field blank, by default.

Est. Remarks

Any remarks related to the estimation of the work order. Mandatory.

Update Requirements

Check this box to update the part and resource requirement details in the execution side.

The box remains checked, by default.

Note: Only tasks whose Estimation Status is “Pending Confirmation”, can be confirmed.

Note: Ensure that for the selected task the Part / Resource / Charge estimates against the Estimated Baseline # is “Zero” for cancelled tasks for which estimates is to be confirmed.

The system performs the following on confirming the estimates.

a.     The execution document must be 'A/C Maint. Exe. Ref.#'

b.     The status of the task must be ‘Planned’ or ‘In-Progress’

c.     The need frequency of the part must be ‘Always’

d.     The part # for which the MR needs to be generated must be be Effective to the aircraft

e.     The process parameter ‘Prevent Material Request?’ for Hold Code of the task must not be 1/Yes in the Define Process Entities activity of Common Master.

If Plan Start Date of the task/discrepancy is a

Need Date of the MR will be set as

Current/Future date

Plan Start Date of the task/discrepancy

Past date

System Current date

In a situation in which multiple material requests are auto-generated by the system, the requests are consolidated on the basis of Need Date or the serviceable request warehouse of the task work center.

To proceed carry out the following:

Refer to “Object Attachments” online help for more details.