Managing quote workings
This activity enables you to record estimates, compute prices and arrive at a Fixed Price based on the specific role of the login user. Option Setting “Allow Estimations & Quote Working by the same User” for a Bid Contract in the Set Sales Process Parameters under Customer business component can be used to control the usage of this activity. Tell me more.
Based on the role of the login user, whether Planner, that is the personnel who estimates and the Commercial Representative that is the personnel who performs the price and quote workings can manage this screen.
After confirmation of the estimations by the Planner, the system queues the Quote Workings document for the commercial representative for further processing.
Note: They system considers the login user as the commercial Rep if the parameter “Allow Estimations & Quote Working by the same User” in the Set Sales Process Parameters under Customer business component is set as ‘No’.
Select the hyperlinked Quoting Workings document number in the ‘Contract Details’ tab page in the ‘Manage Customer Contract’ activity under the ‘Sale Contract’ business component. The “Manage Estimates and Quote Workings” page appears.
The system displays the following field:
Quote Working Document # |
Indicates the associated quote working document number. |
Enter the following fields in the “Search Criteria” group box:
Revision # |
Use the drop-down list box to select the latest revision of the Quote Working Document #. The system lists all the revisions of the Quote Working Document. By default the system displays the latest revision of corresponding quote working document. |
The system displays the following field:
Date |
Indicates the current system date in which the Quote Working document is created. |
Status |
Indicates the status of the Quote Working Document, which could be Draft, Fresh, Confirmed, Cancelled, or Revised'. Click the hyperlinked |
Customer # |
Indicates the customer as in the reference document. |
Object/WS |
Indicates the 'Object' and 'Workscope' combination in Bid contract for which quote working document is created. If there are more than one combination, field displays the value with first Object-Workscope combination + ‘n’ more. |
Currency |
Indicates the currency of the reference document. |
The system displays the following fields in the ‘Additional Details’ group box:
Ref. Doc. Type |
Indicates the type of the reference document which is ‘Bid Contract’. |
Ref. Doc. # |
The number identifying the respective bid contract. |
Working for |
Indicates the 'Object' and 'Workscope' combination in Bid contract for which quote working document is created. If there are more than one combination, field displays the value with first Object-Workscope combination + ‘n’ more. |
Estimation Status |
The estimation status at document level which could be any of the following:
|
Cust. Req. # |
The corresponding 'Bid Request #' for which the Bid Contract is created. |
Purpose/User Status |
Indicates the Purpose / User Status as in the Quote Working Document. |
Category |
Indicates the category to which the Quote Working document belongs. |
Doc. Desc. |
Indicates the textual description of the document as given in the ‘Create Quote Working Document’ screen. |
Est. Notes |
The estimation notes for the Quote Working Document. |
Qt. Working Notes |
The quote working notes for the Quote Working Document. |
Rev. Remarks |
The latest revision comments for Quote Working document. Mandatory if document gets revised. The system leaves this field blank if the Quote Working Document does not have any revisions. |
Canc. Remarks |
The cancellation comments for Quote Working Document which is in cancelled status. The system leaves this field blank if the Quote Working Document is not in cancelled status. |
Toggle and Tile section
The system displays the Toggle and Tile section only if the Assessment tab is completed for the given quote working document. The data count on the tiles represents the line count which are queued up for estimation.
Navigation to the Working multiline can be done by selecting a specific Tile and then select the required tasks that is listed in the Tree after which on clicking the “Move to Working” pushbutton the system moves the selected tasks to the ‘Workscope’ multiline.
Note that the system does not display the Toggle and Tile sections if the Quote Working Document is in ‘Draft’ status. The system displays all the three tabs Assessment/Working/Summary' if the status of the 'Quote Working Document' is other than Draft Status
Select
the icon
to view the Alert Toggle button.
Select
the icon
to view the Exception /
Status Toggle button.
Note that if the user is of both Planner and Commercial Role, the system retrieves all the Tiles.
Note that on click of a Tile, the system retrieves the details of all the detailed tasks uploaded against the particular document in the Tree Section.
Select
the Alert
toggle button to to view and manage immediate actions to be performed.
The system displays the tiles as follows:
# |
Icon |
Status |
System Retrieves |
1 |
Est. Qty < Actual Qty |
Retrieves all the detailed operational tasks for which Est. Qty is lesser than Actual Qty in either “Materials/Resources” multiline. |
|
2 |
Est. Qty < Req. Qty |
Retrieves all the detailed operational tasks for which Est. Qty is lesser than Reqd. Qty in either “Materials/Resources” multiline. |
|
3 |
NRs-Not Estimated |
Retrieves all the detailed operational tasks for which Non-routines are not estimated either at task level or at “Materials/Resources” level. |
|
4 |
Tasks - Not Estimated |
Retrieves all the detailed operational tasks for which either Materials (or) Resources estimation is required but not yet defined/estimated. |
|
5 |
Cost not defined |
Retrieves all the detailed operational tasks for which cost is not updated at “Materials/Resources/Task” level. |
|
6 |
Task Price < Cost |
Retrieves all the detailed operational tasks for which 'Adj. Computed Price - Inclusions' is less than 'Adj. Total Cost - Inclusions' (or) ‘Computed Price - Inclusions' is less than 'Total Cost' against a task line in Workscope Section. |
|
7 |
Part Price < Cost |
Retrieves all the detailed operational tasks for which 'Adj. Computed Price - Inclusions' is less than 'Adj. Total Cost - Inclusions' (or) ‘Computed Price - Inclusions' is less than 'Total Cost' against a task line in Materials Section. |
|
8 |
Resource Price < Cost |
Retrieves all the detailed operational tasks for which 'Adj. Computed Price - Inclusions' is less than 'Adj. Total Cost - Inclusions' (or) ‘Computed Price - Inclusions' is less than 'Total Cost' against a task line in Resources Section. |
Exception/Status toggle button
Select
the Status
toggle button to to view and manage actions to be performed.
The system displays the “Status” toggle button by default. The system displays the tiles as follows:
# |
Icon |
Status |
System Retrieves |
1 |
Pending Workscope |
Retrieves all the Workscope tasks for which 'Detailed operational level tasks are not yet uploaded for the Object-Workscope (or) Object-Workscope-Pricing Model combination'. |
|
2 |
Pending Conf. |
Retrieves all the Workscope tasks for which 'Detailed operational level tasks have been either estimated or updated as not required for Object-Workscope (or) Object-Workscope-Pricing Model combination'. |
|
3 |
Pending Re-estimate |
Retrieves all the Workscope tasks for which 'Re-estimate’ action is initiated' for Object-Workscope (or) Object-Workscope-Pricing Model combination'. |
|
4 |
All Tasks |
Retrieves all the detailed operational tasks that are uploaded against the quote working document. |
|
5 |
All Pending Estimates |
Retrieves all the detailed operational tasks for which either Materials or Resources estimation is required but not yet defined or estimated. |
|
6 |
Pending Est. - Mat |
Retrieves all the detailed operational tasks for which Materials estimation is required but not yet defined / estimated. |
|
7 |
Pending Est. - Res |
Retrieves all the detailed operational tasks for which Resource estimation is required but not yet defined / estimated. |
|
8 |
Pending Est. – NRs |
Retrieves all the detailed operational tasks for which Non-routines are not estimated either at task level or at Materials / Resources level. |
|
9 |
Tasks not Priced |
Retrieves all the detailed operational tasks for which tasks are not yet priced but cost is defined. |
|
10 |
Parts not Priced |
Retrieves all the detailed operational tasks for which parts are not yet priced but part cost is defined. |
|
11 |
Resources not Priced |
Retrieves all the detailed operational tasks for which Resources are not yet priced but resource cost is defined. |
Select the “Assessment” tab to initiate an estimation action against the Object-Workscope (or) Object-Workscope-Pricing Model combination.
Select the “Working” tab add details of operational tasks for the given Workscope tasks and work on cost and price for those tasks.
Select the “Summary” tab to review the cost/price workings against each combination.
Note: The system displays only the “Working” tab for Planner role login logging from the "Record Work Estimates" activity under the "Work Monitoring & Control" business component.
The system displays the following fields in the ‘Record Statistics’ group box:
Created by |
The login ID of the user who created the quote working document. |
Created Date |
The date on which the quote working document is created. |
Last Modified by |
The login ID of the user who has last modified the quote working document. |
Last Modified Date |
The date on which the quote working document was last modified. |
Confirmed by |
The login user who confirmed the quote working document. |
Confirmed Date |
The date on which the quote working document was confirmed. |
This tab enables the commercial representative to assess the Quote Working document. Many pricing models as per the requirement can be added for the given Object-Workscope combination.
Note: This tab is displayed only if the login user is a commercial representative that is personnel who works on the price and quotes.
The commercial role initiates an estimation action against the Object-Workscope which are defaulted from the Sale Contract. The system allows the user to add multiple pricing model against an ‘Object-Workscope’ combination to differentiate the estimates / pricing level and give an option to customer to choose the pricing.
Header Section
Enter the following fields:
Object |
Use the drop-down list box to specify the object against which estimation action is to be initiated. The system lists all the object references given in reference document (Bid Contract) against which the Quote working document is created, along with the value 'All'. By default the system displays 'All' in this field. |
Workscope |
Use the drop-down list box to specify the workscope against which estimation action is to be initiated. The system lists all the workscope given for the value selected in 'Object' combo in the reference document against which the Quote working document is created, along with value 'All'. By default the system displays 'All' in this field. |
Pricing Model |
Use the drop-down list box to specify the pricing model to be added against the Object-Workscope. The system lists all the pricing models for the “Object - Workscope' combination as selected in the Object and Workscope combo, along with the value 'All'. |
Click the “Get” pushbutton to view details of the 'Object-Workscope-Pricing Model' combination selected in the Tree Grid Multiline.
Tree Grid Multiline section
The system displays the following fields:
Est. |
Indicates color coded values representing the status of the estimates. The system leaves this field blank if the estimates are not initiated.
|
Qt. |
Indicates color coded values representing the status of the quote. The system leaves this field blank if the estimations are not yet confirmed.
|
Enter the following fields:
Object-WS-Pricing Model |
Tree Grid displaying the corresponding Object-Workscope-Pricing Model Combination. |
Est. Action |
Use the drop-down list box to select the estimation action, which could be any of the following: Mandatory
|
Est. For |
Use the drop-down list box to specify the object for which estimation to be done. Mandatory. The system lists the following options:
|
Est. Remarks |
Any comments pertaining to the estimation. |
Est. By |
Use the drop-down list box to specify the personnel who has to perform the estimation. (Mandatory) You can select from the below options:
|
Emp. Code |
The code identifyig the employee. Search facility available. |
Est. Level |
Use the drop-down list box to select the level at which estimation is done. (Mandatory).
|
The system displays the following fields:
Obj. Eff. Code |
Indicates the respective Part/Aircraft Effectivity code from bid contract at the parent node for the given record. |
WS Code |
Indicates the respective Work Scope code from bid contract at the child nodes for the given record. |
Approval Status |
Indicates the Customer Approval status of the object-work scope combination against the Bid Proposal for the Fixed price quoted. |
Button Section
Select the “Add Pricing Model” button to add pricing model details. The system launches the “Add Pricing Model” popup.
Note that you can add pricing model details only for those records which are not yet estimated.
The system displays the color code for the estimation as follows:
Estimate Completed |
|
Estimate Pending |
|
Quotation Completed |
|
Quotation Pending |
Enter the following field:
Rev. Remarks |
Any note pertaining to the revision of the estimation. |
Select the “Save” button.
Note: Ensure that at least one multiline from the Tree Grid is selected.
Note that the system allows saving of details only for those quote working documents that are in other than “Revised or Cancelled” status.
The system performs the following:
Generates a new Quote
Working Document in “Fresh” status when all the Object-Workscope (or)
Object-Workscope-Pricing Model combination are dispositioned for estimation.Ø
Select the “Cancel” button.
The system performs the following:
Launches
a popup to cancel the record with Cancellation Remarks.
Note: Does not allow the user to cancel the previous revision of the Quote Working Document or Quote Working Document that is in “Confirmed” status.
In this tab you can add operational task details for a given Workscope task and independently work on cost and price for those tasks.
Tree Section – In this section you can view details of the status of each of the tasks.
Record Workings Section – In this section you can add details of operational tasks against ‘Object-Workscope-Pricing Model’ combination and enter values of cost and price against the task added.
Note that the system displays details in this tab based on the login user role as given below:
· Planner: The system retrieves all the Object-Workscope combinations for which assessments are completed against Quote Working document.
· Commercials: The system retrieves the Object-Workscope combinations for which the estimates are confirmed.
Tree Section
This section enables you to select a specific task from the tree and move that particular task details to the ‘Working’ multiline for further proceedings.
Note: The status of the Tree Grid is based on the Planner/ Commercials Role. For Planner Role, the Tree Grid task status shows estimations and for Commercial Role, it shows status of Quotations.
Tree Grid
Objects - Workscope Section
Click the “Refresh” to retrieve any newly added tasks against an Object-Workscope combination and to update the color coding of the status of tasks.
The system displays the Tree Grid as follows:
Tree Structure:
> Object 1
> Work scope (or) Work scope-Pricing Model Combination
> Operational Task 1
> Operational Task 2
> Status: The grid displays status of the Task of an object in Quote Working document, which could be any of the following:.
Pending: Indicates that all the tasks which are uploaded against the object work scope but not yet saved against the quote workings document.
In-progress: Indicates that all the tasks which are saved against the quote workings document and Estimations/Quotations are being done or yet to be done (till confirm estimations)
Completed: Indicates that all Tasks under the Object- Work Scope- Pricing Model combination which are in confirmed estimates/quote workings confirmed status. It also includes all the tasks for which estimation is set as Not Required under this node
Click the “Move to Working” pushbutton to transfer the selected operational’ tasks to the Record Workings’ multiline.
Note: Ensure that at least one record is selected in the Tree Grid
Note: Ensure that not more than one Object-Workscope-Pricing Model Combination is selected.
Note: Operational tasks are not selected across Object-Workscope-Pricing Model Combination is selected.
Tree Grid Color Codes
Planner Role |
|
Commercial Role Commercial & Planner Role |
|
Status |
Color Code |
Status |
Color Code |
Work scope not done |
Black |
Quote not started |
Blue |
Estimation not started |
Blue |
Quote In Progress |
Orange |
Estimation In Progress |
Orange |
Quote Completed |
Green |
Estimation Completed |
Green |
|
|
Record Workings Section
Header Section
Enter the following fields:
Object |
Use the drop-down list box to the object for which record working is to be done. The system lists all the objects from Quote working Document. |
Work Scope |
Use the drop-down list box to Workscope for which record working is to be done. The system lists all the all the work scopes for object selected from Quote working document. |
Pricing Model |
Use the drop-down list box to specify the pricing model for which record workings is to be done. The system lists the corresponding pricing model for values selected in 'Object' and 'Work scope' combo Note that the system does not display this field if the role of the login user is Planner. |
Status |
The status of quote working document, which could be any of the following:
|
The system displays the following fields:
Est. Notes |
Indicates the corresponding estimation remarks given against the Object-Workscope combination in multiline of Assessment tab. |
Est. For |
Indicates the corresponding Est. for given against the Object-Worksscope combination in Assessment tab |
Quote Remarks |
Any remarks against Object-WS-Pricing model combination specified by the planner/commercial role. |
Click the “Get” pushbutton to retrieve all the operational tasks in Work Scope multiline for 'Object - WS - Pricing model' (or) 'Object - WS - Estimation Model' specified in the header combo..
Button Bar Section
Select the “Workscope” button bar to add task level details indicating the tasks to be performed based on the login user role.
Select the “Materials button bar to add estimation details of the materials required to perform the tasks added in the ‘Workscope’ button bar.
Select the “Resources button bar to add estimation details of the resources required for the tasks added in the Workscope button bar.
Select the “Charges" button bar to add estimation of other charges, for example Travel expenses that does not come under the Material or Resource category.
Enter the following fields in the “Search Criteria” section:
Search By |
Use the drop-down list box to specify the basis on which you wish to search and retrieve details in the multiline. The system lists the following options: · Task # · Total Cost greater Than · Total Cost lesser than By default the system leaves this field blank. |
|
In the editable field alongside, specify the value corresponding to the “Search by” selected. |
Addl. Search |
Use the drop-down list box to select the additional search criteria based on which you wish to retrieve details in the multiline. The system lists the following options for Planner role:: · Est. Status · Est. History · NRs Not Estimated · Req. Not Avbl. Note that the system displays the option NRs Not Estimated alone in this field if the login user role is Commercials. By default the system leaves this field blank. |
|
In the adjacent combo control use the drop-down list box to select a value corresponding to the item selected in the ‘Addl. Search’ field. The system lists options as follows for Planner Role: If 'Est. Status' is selected in 'Addl. Search':
If 'Est. History' is selected in 'Addl. Search':
If 'NRs not estimated' and 'Req. Not Avbl.' is selected in 'Addl. Search
Note that the system leaves this field blank if the role of the login user is commercials. |
Exceptions |
Use the drop-down list box to specify the exceptions in cost/price computation against the task details. The system lists the following options: · Price < Cost · Not Priced Tasks Note that the system displays this field only if the login user is of Commercial role. By default the system leaves this field blank. |
Click the “Filter” pushbutton to retrieve details against the Object-Workscope-Pricing Model based on the filter criteria
Enter the following fields in the “Pricelist Info” section:
Note: The system displays the Pricelist Info section only for the Commercial role login user.
Part Pricelist |
The number identifying the part pricelist. Data entry in this field is Mandatory if the ‘Part Pricelist’ 'Standard Cost' / 'Standard Purchase Pricelist specified as the Cost From. Ensure that the value entered in this field is a valid 'Part Pricelist' of type 'Ref. Catalogue' or 'OEM Pricelist' and is not a regular pricelist. Help facility available. |
Service Pricelist |
The number identifying the service pricelist. Help facility available. |
The system displays the following fields in the “Task Details” multiline:
ES |
Color coded icon based on the status of the estimation of the task. |
QS |
Color coded icon based on the status of the quote of the task. |
In the Price Excp. group, the system displays the following:
M |
The estimation status for materials. The system displays the following icon:
By default the system leaves this field blank. |
R |
The estimation status for materials. The system displays the following:
By default the system leaves this field blank. |
C |
The estimation status for charges. The system displays the following:
By default the system leaves this field blank. |
Enter the following fields:
Task # |
The number identifying the task.. Mandatory. Help facility available. |
Task Seq. # |
The sequence number of the added tasks. |
The system displays the following fields:
Task Desc. |
A brief textual description of the task. |
The system displays the following fields in the “Req. Avbl?” group:
M |
Indicates whether the materials is set as required/not required in the task master. The system displays as follows:
|
R |
Indicates whether the resources is set as Required/Not required in the task master. The system displays as follows:
|
The system displays the following fields in the “Defined?” group:
M |
Indicates whether the materials is set as required in the task master and defined in material multiline. The system displays as follows:
|
R |
Indicates whether the resources is set as required in the task master and defined in resource multiline. The system displays as follows:
|
C |
Indicates whether the charges are defined in the Charges multiline. The system displays as follows:
The system leaves this field blank if Charges are not defined against a task and defined in the Charges tab. |
The system displays the following fields in the “Non-Rtn Defined?” group:
M |
|
R |
The system leaves this field blank if non-routines are not defined for a task in the Resources. |
The system displays the following fields in the “Total Cost” group:
Mat. |
Displays the value with entire material cost against the task line by adding column 'Total - Total Cost' in Materials Multiline |
Res. |
Displays the value with entire resource cost against the task line by adding column 'Total - Total Cost' in Resources multiline |
Charges |
Displays the value with entire charges cost against the task line by adding column 'Amount' in Charges multiline |
Enter the following fields:
Task Lvl. NRs |
Any Non-routine tasks against the tasks can be defined against this field. Ensure that the value entered in this field is a positive integer greater than zero. |
The system displays the following fields:
Total |
Indicates the sum of 'Materials, Resources, Charges and Task lvl. Non Rtns' column in this column grouping in Work scope multiline. |
Enter the following fields:
Est. Remarks |
Any notes pertaining to the estimation. |
Exclude? |
Use the drop-down list box to specify any exclusions against the task line. The system lists the following options: · Regular · Non-Routines · Both |
Enter the following fields in the Markup – Task Lvl NRs group:
Mark-up % |
Any markup that needs to be added against cost of Task Level NR can be specified as percentage. Ensure that the value entered in this field ranges from 0 to 100. |
Value |
Mark up Value that should be added against Task Level NR cost can be specified. |
The system displays the following fields in the “Computed Price Inclusion” group:
The system displays the following fields with below logic if the parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set either as “No" (or) "Adjust Task Probability Rates'
Mat. |
Sum of the 'Total – Extd. Price Inclusions' column in Materials Multiline. |
Res. |
Sum of the 'Total - Extd. Price Inclusions' column in Resources Multiline. |
Charges |
Sum of the 'Total Value' column in Charges Multiline. |
Task Lvl. NRs |
Addition of 'Mark-up Value' in the 'Mark-up Task Lvl NRs' column group with 'Task Lvl. Non-Rtn.' in 'Total Cost' column group in ‘Work Scope’ Multiline. |
Total |
Sum of 'Materials, Resources, Charges and Task lvl. NRs' column in this column group. |
The system displays the following fields with below logic if the parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set either as “Adjust for Part probability rate" (or) " Adjust both Task & Part Probability Rates”
Mat. |
Sum of the 'Total – Adj. Price Inclusions' column in Materials Multiline. |
Res. |
Sum of the 'Total - Extd. Price Inclusions' column in Resources Multiline. |
Charges |
Sum of the 'Total Value' column in Charges Multiline. |
Task Lvl. NRs |
Addition of 'Mark-up Value' in the 'Mark-up Task Lvl NRs' column group with 'Task Lvl. Non-Rtn.' in 'Total Cost' column group in ‘Work Scope’ Multiline. |
Total |
Sum of 'Materials, Resources, Charges and Task Lvl. NRs' column in this column group. |
The system displays the following fields in the “Total Cost - Inclusion group” group:
The system displays the following with below logic, if the parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set either as 'Adjust for Part Probability Rate" (or) "Adjust both Task & Part Probability Rates'
Mat. |
Sum of the 'Total - Adj. Total Cost Inclusions' column in Materials Multiline |
Res. |
Sum of 'Total - Total Cost Inclusions' column in Resources Multiline. |
Charges |
Sum of 'Amount ' column in Charges Multiline. |
Task Lvl. NRs |
The value from 'Task Lvl. NR column' in the 'Total Cost' column group in Work scope Multiline |
Total |
Sum of 'Materials, Resources, Charges and Task Lvl. NRs' columns in this column grouping. |
The system displays the following with below logic, if the parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set either as 'No" (or) "Adjust for Task Probability Rates'
Mat. |
Sum of the 'Total - Total Cost Inclusions' column in Materials Multiline |
Res. |
Sum of 'Total - Total Cost Inclusions' column in Resources Multiline. |
Charges |
Sum of 'Amount ' column in Charges Multiline. |
Task Lvl. NRs |
The value from 'Task Lvl. NR column' in the 'Total Cost' column group in Work scope Multiline |
Total |
Sum of 'Materials, Resources, Charges and Task Lvl. NRs' columns in this column grouping. |
The system displays the following fields in the “Profit / (Loss) – Inclusion” group:
Mat. |
(Materials - Computed Price Inclusions) - (Materials - Total Cost - Inclusions) |
Res. |
'(Resources - Computed Price Inclusions) - (Resources - Total Cost - Inclusions) |
Charges |
'(Charges - Computed Price Inclusions) - (Charges - Total Cost - Inclusions) |
Task Lvl. NRs |
'(Task Lvl. NRs - Computed Price Inclusions) - (Task Lvl. NRs - Total Cost - Inclusions) |
Total |
Sum of Materials, Resources, Charges and Task Lvl. NRs’ columns in this column grouping |
Enter the following fields:
Task Prob. Rate |
Probability or happening Rate of the task in multiline can be specified. Data entry in this field is mandatory if the parameter 'Consider Task. Prob Rate for Price Computation for Quote Working?' is set as 'Yes' in 'Set Sales Process Parameter' screen. Ensure that the value entered in this field is between the range of 0 to 100 only. |
The system displays the following fields in the “Adj. Computed Price Inclusions” only if the parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set either as 'Adjust Both Tasks & Part Probability Rate' (or) 'Adjust Task Probability Rate':
Mat. |
Task Prob. Rate * Materials - Computed Price Inclusions. |
Res. |
Task Prob. Rate * Resources - Computed Price Inclusions. |
Charges |
Task Prob. Rate * Charges - Computed Price Inclusions. |
Task Lvl. NRs |
Task Prob. Rate * Task Lvl. NRs - Computed Price Inclusions. |
Total |
Sum of 'Materials, Resources, Charges and Task Lvl. NRs' columns in this column grouping. |
The system displays the following fields in the “Adj. Cost – Inclusion” group only if the parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set either as 'Adjust Both Tasks & Part Probability Rate' (or) 'Adjust Task Probability Rate':
Mat. |
Task Prob. Rate * Materials - Total Cost Inclusions. |
Res. |
Task Prob. Rate * Resources - Total Cost Inclusions. |
Charges |
Task Prob. Rate * Charges - Total Cost Inclusions. |
Task Lvl. NRs |
Task Prob. Rate * Task Lvl. NRs - Total Cost Inclusions. |
Total |
Sum of 'Materials, Resources, Charges and Task Lvl. NRs’ columns in this column grouping. |
The system displays the following fields in the “Adjusted Profit / (Loss) – Inclusion” group only if the parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set either as 'Adjust Both Tasks & Part Probability Rate' (or) 'Adjust Task Probability Rate'
Mat. |
Task Prob. Rate * Materials - Profit/ (Loss) Inclusions |
Res. |
Task Prob. Rate * Resources - Profit/ (Loss) Inclusions |
Charges |
Task Prob. Rate * Charges - Profit/ (Loss) Inclusions |
Task Lvl. NRs |
Task Prob. Rate * Task Lvl. NRs - Profit/ (Loss) Inclusions |
Total |
Sum of 'Materials, Resources, Charges and Task Lvl. NRs' column in this column grouping |
The system displays the following fields in the “Exclusions” group:
Total Cost |
Sum of Price - Exclusion' in Materials Multiline and 'Price-Exclusion' in Resource Multiline against the task |
Total Price |
Sum of 'Cost - Exclusion' in Materials Multiline and 'Cost-Exclusion' in Resource Multiline against the task |
Profit / (Loss) |
Difference between 'Total Price' and 'Total Cost' in this column grouping |
Enter the following fields:
Est. Elapsed Time |
The estimated elapsed time required for the resource to complete the task |
UOM |
Use the drop-down list box the unit of measurement. Data selection in this field is mandatory. The system lists the following option: · Hours |
Est. Mod Notes |
Any textual comments on the modifications made to the estimations. |
Doc. Mod Notes |
Any textual comments on the modifications made to the Quote Working document. Data entry in this field is mandatory for any task details queued up for re-estimate is modified. |
Qt. Working Notes |
A brief textual description of the Quote Workings. |
Remarks |
Any comments pertaining to the Quote Workings. |
The system displays the following fields in the “Summary” section:
Note: The system displays this section only if the login user is in Planner role.
Note: The system displays the total number of skill hours estimated against the Object-Work Scope – Pricing Model combination in the top right corner in the Summary section.
Materials |
Cost: Indicates the sum of values in column 'Materials - Total Cost' in Work scope tab against all the tasks for selected Object - WS Combination. |
Resources |
Cost: Indicates the sum of values in column 'Resources - Total Cost' in Work scope tab against all the tasks for selected Object - WS Combination. |
Charges |
Cost: Indicates the sum of values in column 'Charges - Total Cost' in Work scope tab against all the tasks for selected Object - WS Combination. |
Task Lvl. NRs |
Cost: Indicates the sum of values in column 'Task Lvl. NRs. - Total Cost' in Work scope tab against all the tasks for selected Object - WS Combination. |
Total |
Cost: Indicates the sum of values of 'Materials', 'Resources', 'Charges' and 'Non-Routines' which are derived in Cost summary. |
The system displays the following fields in the “Summary” section
Note: The system displays this section only if the login user is in Commercial role.
If the 'Adjust the Cost & Price Info based on the Probability Rate?' is set as 'Adjust Task Probability Rate' or 'Adjust both Task & Part Probability Rates'
Materials |
Cost: Displays the added values in column 'Materials - Adj. Cost Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination. Price: Displays the added values in column 'Materials - Adj. Computed Price Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination. |
Resources |
Cost: Displays the added values in column 'Resources - Adj. Cost Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination. Price: Displays the added values in column 'Resources - Adj. Computed Price Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination |
Charges |
Cost: Displays added values in column 'Charges - Adj. Cost Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination Price: Displays added values in column 'Charges - Adj. Computed Price Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination |
Non-Routines |
Cost: Displays added adding the values in column 'Task Lvl. NRs. - Adj. Cost Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination. Price: Displays the added the values in column 'Task Lvl. NRs - Adj. Computed Price Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination |
Total |
Cost: Displays the added values of 'Materials', 'Resources', 'Charges' and 'Non-Routines' which are derived against the control of Cost in summary. Price: Displays the added values of 'Materials', 'Resources', 'Charges' and 'Non-Routines' which are derived against the control of Price in summary. |
The system displays the following fields in the “Summary” section if parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set as 'No' or 'Adjust Part Probability Rates')
Materials |
Cost: Displays the added values in column 'Materials - Total Cost Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination Price: Displays the added values in column 'Materials - Computed Price Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination. |
Resources |
Cost: Displays the added values in column 'Resources - Total Cost Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination Price: Displays the added values in column 'Resources - Computed Price Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination |
Charges |
Cost: Displays the added values in column 'Charges - Total Cost Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination. Price: Displays the added values in column 'Charges - Computed Price Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination |
Non-Routines |
Cost: Displays the added values in column 'Task Lvl. NRs. - Total Cost Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination. Price: Displays the added values in column 'Task Lvl. NRs - Computed Price Inclusions' in Workscope multiline against all the tasks for selected Object – Workscope combination |
Total |
Cost: Displays the added values of 'Materials', 'Resources', 'Charges' and 'Non-Routines' which are derived against the control of Cost in summary. >> Price: Displays the added values of ('Materials', 'Resources', 'Charges' and 'Non-Routines' which are derived against the control of Price in summary. |
Enter the following fields in the “Object Level Non-Routines” section:
Key Links |
Use the drop-down list box to select the key links to navigate to various screen from Quote Working document.
|
Save Action |
Use the drop-down list box to select the action to be saved. The system lists the following options for login user with both Planner and Commercial roles: · Est. Not Reqd. · Clear Price Exceptions The system lists the option ‘Clear Price Exceptions’ only if the login user has a Commercial role. |
Click the “Save Estimates” pushbutton to save the estimation details.
Click the “Confirm Estimates” pushbutton to confirm the estimations.
Click the “Save” pushbutton to save the pricing details.
Note: Ensure that at least one record is selected in the multiline if pricing exception is specified against the task.
Enter the following fields in the “Search Criteria” section:
Search By |
Use the drop-down list box to specify the basis on which you wish to retrieve details in the multiline. The system lists the following options: · Task # · Cost per unit greater Than · Total Cost greater than · Price per unit greater than · Mark up per unit greater than · Extd. price greater than · Part # By default the system leaves this field blank. |
|
In the editable field alongside, specify the value corresponding to the “Search by” selected. |
Addl. Search |
Use the drop-down list box to select additional search criteria based on which you wish to retrieve details in the multiline. The system lists the following options: · NRs Not Estimated · Est. Status · Est. History · Stock Status By default the system leaves this field blank. |
|
In the additional combo control, use the drop-down list box to select the additional search criteria based on which you wish to retrieve details in the multiline. The system lists options as follows :
|
Exceptions |
Use the drop-down list box to specify the exceptions in Materials multiline. The system lists the following options: · Price < Cost · Est. Qty < Req. Qty · NR Est. < Act Qty |
Click the “Filter” pushbutton to retrieve only details of the selected tasks.
Enter the following fields in the “Part Details” section:
Cost From |
Use the drop-down list box to specify the source from where the cost of the part is to be taken. You can select from the following options:
By default the system leaves this field blank. |
|
In the editable field alongside, enter the value corresponding to the ‘Part Pricelist #” specified. Help facility available |
Click the “Get Cost’ pushbutton to retrieve details of Cost / Unit.
Enter the following fields in the multiline:
The system displays the following field:
ES |
Indicates the status of the estimation for materials which could be any of the following:
|
QS |
Indicates the status of the quote for the materials, which could be either of the following:
|
Enter the following fields in the multiline:
Task # |
The number identifying the task for which material estimation is done. Mandatory. Help facility available |
Task Seq. # |
The number identifying the sequence of the task for which material estimation is to be done. |
Part # |
The number identifying the part for which estimation is done. Mandatory. Help facility available |
UOM |
Use the drop-down list box to specify the unit of measurement. Mandatory. |
The system displays the following field:
Req. Qty |
The quantity of material required for the task based on the task master. |
NR Qty. – Act. |
The quantity of the actual non-routine parts for the given task based on previous history. |
Enter the following fields in the “Est. Qty” group:
Reg. |
Quantity of part which is required for estimation on a regular basis. Ensure that the value entered in this field is a positive integer greater than 0. |
Non-Rtn. |
Quantity of part that is not planned for regular basis but as non-routines based on consumption history, which is required for estimation. Ensure that the value entered in this field is a positive integer greater than 0. |
The system displays the following field:
Total |
Regular - Est. Qty + Non Routine - Est. Qty' |
Enter the following fields:
Stock Status |
Use the drop-down list box to specify the stock status. The system lists all the active stock statuses as defined in the “View User Defined Stock Status” activity of the “User Defined Stock Status” business component. |
Part Condition |
Use the drop-down list box to select the condition of the part which is to be estimated. The system lists the following options:
By default the system leaves this field blank. |
Cost / Unit |
The cost per unit of part. |
The system displays the following fields in the “Total Cost” group:
Reg. |
Regular - Est. Qty * Cost per Unit |
Non Rtn. |
Non Routine - Est. Qty * Cost per unit |
Total |
Regular - Total Cost + Non Routine - Total Cost |
Enter the following fields:
Exclude? |
Use the drop-down list box to select exclusions in the material multiline. The system lists the following values:
By default the system leaves this field blank. |
Base Rate / Unit |
The base rate per unit for the part. |
Enter the following fields in the “Markup / Unit” group:
Percentage |
Any markup that needs to be added against Base Rate/Unit can be specified as percentage. Ensure that the value entered in this field ranges from 0 to 100. |
Value |
Base Rate/Unit * (Mark up % / 100)' |
The system displays the following field:
Price / Unit |
Base Rate/Unit + Mark-up Value |
The system displays the following fields in the “Extd. Base Price - Inclusions” group:
Reg. |
Regular - Est. Qty * Base Rate/Unit' |
Non Rtn. |
Non Routine - Est. Qty * Base Rate/Unit |
Total |
Regular - Extd. Base Price + Non Routine - Extd. Base Price |
The system displays the following fields in the “Extd. Mark Up - Inclusions” group:
Reg. |
Regular - Est. Qty * Mark-up Value |
Non Rtn. |
Non Routine - Est. Qty * Mark-up Value |
Total |
Regular - Extd. Mark-up + Non Routine - Extd. Mark-up |
The system displays the following fields in the “Extd. Price - Inclusions” group:
Reg. |
Regular - Est. Qty * Price per unit' (or) 'Regular - Extd. base Price + Regular - Extd. Mark-up |
Non Rtn. |
Non Routine - Est. Qty * Price per unit' (or) 'Non Routine - Extd. base Price + Non Routine - Extd. Mark-up |
Total |
Regular - Extd. Price + Non Routine - Extd. Price |
The system displays the following fields in the “Total Cost - Inclusions” group:
Reg. |
Regular - Total Cost' from Materials multiline, if Exclude is not set as 'Regular' or 'Both' |
Non Rtn. |
Non Routine - Total Cost' from Materials multiline, if Exclude is not set as 'Non-routine' or 'Both' |
Total |
Regular - Total Cost Inclusions + Non-Routines - Total Cost Inclusions |
The system displays the following fields in the “Profit / (Loss) - Inclusions” group:
Reg. |
(Regular - Extd. Price Inclusions) - (Regular - Total Cost Inclusions)' |
Non Rtn. |
(Non Routine - Extd. Price Inclusions) - (Non Routine - Total Cost Inclusions) |
Total |
(Total - Extd. Price Inclusions) - (Total - Total Cost Inclusions) |
The system displays the following fields in the “Adj. Price - Inclusions grouping” only if the parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set either as 'Adjust Both Tasks & Part Probability Rate' (or) 'Adjust Part Probability Rate':
Reg. |
(Reqd. Probability /100)* Regular – Extd. Price Inclusions |
|
Non Rtn. |
(Reqd. Probability /100) * Non Routine – Extd. Price Inclusions' |
|
Total |
(Reqd. Probability /100)* Total – Extd. Price Inclusions |
|
The system displays the following fields in the “Adj. Total Cost - Inclusions grouping” only if the parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set either as 'Adjust Both Tasks & Part Probability Rate' (or) 'Adjust Part Probability Rate':
Reg. |
(Reqd. Probability /100)* Regular - Total Cost Inclusions |
Non Rtn. |
(Reqd. Probability /100) * Non Routine - Total Cost Inclusions' |
Total |
(Reqd. Probability /100)* Total - Total Cost Inclusions |
The system displays the following fields in the “Adj. Profit/(Loss) - Inclusions grouping” only if the parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set either as 'Adjust Both Tasks & Part Probability Rate' (or) 'Adjust Part Probability Rate':
Reg. |
(Reqd. Probability /100)* Regular – Profit/(Loss) Inclusions |
Non Rtn. |
(Reqd. Probability /100) * Non Routine - Profit/(Loss) Inclusions |
Total |
(Reqd. Probability /100)* Total - Profit/(Loss) Inclusions |
Enter the following field:
Est. Remarks |
Any comment pertaining to the material estimations. |
The system displays the following fields in the “Exclusions” group:
Price |
Sum of all Extd. Price in both Regular as well as Non Routines whichever are excluded. |
Cost |
Sum of all Total Cost in both Regular as well as Non Routines whichever are excluded. |
Profit |
(Price-Exclusions) - (Cost-Exclusions). |
Enter the following field:
Est. Notes |
A brief textual note on the estimation of materials |
Qt. Working Notes |
A brief textual note on the Quote Working document. |
The system displays the following fields:
PMA? |
Indicates whether the part is a PMA part, which could be ‘Yes’ or ‘No’. |
Part Type |
The type of part as in the Part master. |
Part Class |
The classification to which the part belongs as in the Part master. |
Task Desc. |
A brief textual note on the task that is added. |
Part Desc. |
A brief description of the part specified as defined in the Part master. |
Enter the following field:
Est. Mod. Notes |
A textual note on the modifications made in estimation of materials in the Quote Working document. |
Doc. Mod. Notes |
A textual note on the modifications in price of materials made in the Quote Working document. |
The system displays the following fields:
Base Rate PPL Curr. |
If any part pricelist is used to define the base rate/unit for materials, then display the corresponding currency of part from that pricelist. |
The system displays the following fields in the “Cost Summary” section:
Note: The system displays this section only if the login user is in Planner role.
Regular |
Cost: Displays the added value of the Regular' column under the 'Total Cost' column grouping for all the tasks lines, for the given 'Object-Workscope-Pricing Model' combination |
Non-Routines |
Cost: Displays the added value of the “Non Routine' column under the 'Total Cost' column grouping for all the tasks lines, for the given 'Object- Workscope -Pricing Model' combination |
Total |
Cost: Displays the added value of 'Total' column under the 'Total Cost' column grouping for all the tasks lines, for the given 'Object- Workscope -Pricing Model' combination |
The system displays the following fields in the “Summary” section if parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set as 'Adjust Part Probability Rate' or 'Adjust both Task & Part Probability Rates':
Note: The system displays this section only if the login user is in Commercial role.
Regular |
Price: Displays the value by adding 'Regular' column under the 'Adj. Price Inclusions' column grouping for all the tasks line items for the given 'Object- Workscope -Pricing Model' combination Cost: Displays the value by adding 'Regular' column under the 'Total Cost' column grouping for all the tasks line items, for the given 'Object- Workscope -Pricing Model' combination |
Non-Routine |
Price: Displays the value by adding 'Non-Routine' column under the 'Adj. Price Inclusions' column grouping for all the tasks line items, for the given 'Object-Work scope-Pricing Model' combination Cost: Displays the value by adding 'Non Routine' column under the 'Total Cost' column grouping for all the tasks line items, for the given 'Object- Workscope -Pricing Model' combination |
Total |
Cost: Displays the value by adding 'Total' column under the 'Total Cost' column grouping for all the tasks line items, for the given 'Object- Workscope -Pricing Model' combination Price: Display the value by adding 'Total' column under the 'Adj. Price Inclusions' column grouping for all the tasks line items, for the given 'Object- Workscope -Pricing Model' combination |
The system displays the following fields in the “Summary” section if parameter 'Adjust the Cost & Price Info based on the Probability Rate?' is set as 'No' or 'Adjust Task Probability Rates
Note: The system displays this section only if the login user is in Commercial role.
Regular |
Price: Displays the value by adding 'Regular' column under the 'Extd. Price Inclusions' column grouping for all the tasks line items, for the given 'Object- Workscope -Pricing Model' combination Cost: Display the value by adding 'Regular' column under the 'Total Cost Inclusions' column grouping for all the tasks line items, for the given 'Object- Workscope -Pricing Model' combination |
Non-Routine |
Price: Display the value by adding 'Non-Routine' column under the 'Extd. Price Inclusions' column grouping for all the tasks line items, for the given 'Object- Workscope -Pricing Model' combination Cost: Display the value by adding 'Non Routine' column under the 'Total Cost Inclusions' column grouping for all the tasks line items, for the given 'Object- Workscope -Pricing Model' combination |
Total |
Price: Display the value by adding 'Total' column under the 'Extd. Price Inclusions' column grouping for all the tasks line items, for the given 'Object- Workscope -Pricing Model' combination Cost: Display the value by adding 'Total' column under the 'Total Cost Inclusions' column grouping for all the tasks line items, for the given 'Object- Workscope Work scope-Pricing Model' combination |
Click the “Get Requirements” pushbutton to retrieve part requirements from the Task master.
Note: Ensure that at least one record in the multiline is selected.
Note: Ensure that the Quote Working document is in status other than ‘Confirmed’, ‘Cancelled’ or ‘Revised’.
Click the “Get NR Actuals” pushbutton to retrieve details of all the 'Routines' and 'Non-Routines' based on actual history.
Click the “Compute” pushbutton to re-run the computation logic for all the columns in the Materials multiline.
Click the “Save Part Estimates” pushbutton to retrieve update all the estimations made.
Click the “Save Part Pricing” pushbutton to save pricing against the materials.
Enter the following fields in the “Search Criteria” section:
Search By |
Use the drop-down list box to specify the basis on which you wish to retrieve details in the multiline. The system lists the following options: · Task # · Res. # · Cost per unit greater Than · Total Cost greater than · Price per unit greater than · Mark up per unit greater than · Extd. price greater than By default the system leaves this field blank. |
|
In the editable field alongside, enter a value corresponding to the ‘Search by’ specified. |
Addl. Search |
Use the drop-down list box to select the basis on which you wish to search and retrieve details in the multiline. The system lists the following options: · NRs Not Estimated · Attendance Type · Res. Type · Est. Status · Est. History By default the system leaves this field blank. |
|
In the adjacent combo control use the drop-down list box to select a value corresponding to the item selected in the ‘Addl. Search’ field. The system lists options as follows · If 'Est. Status' is selected in 'Addl. Search': · Completed · Pending · If 'Est. History' is selected in 'Addl. Search': · Estimation ID which are auto-generated during re-estimate. · If ‘Res. Type’ is selected in the ‘Addl. Search’:
· If 'Attendance Type is selected in the 'Addl. Search”
If “NRs Not Estimated’ is selected in ‘Addl. Search’, then load the value as ‘Blank’ |
Exceptions |
Use the drop-down list box to filter the exceptions in the Resources Multiline. The system lists the following options: · Price < Cost · Est. Qty < Req. Qty · NR Est. < Act Qty |
Click the “Filter” pushbutton to retrieve only details of the selected tasks.
Enter the following fields in the “Resource Details” section:
Cost From |
Use the drop-down list box to specify the source from where the cost of the resource is to be taken. You can select from the following options: § Service Pricelist By default the system leaves this field blank. |
|
In the editable field alongside, enter the value corresponding to the ‘Service Pricelist’ is specified. Help facility available |
Click the “Get Cost’ pushbutton to retrieve details of Cost for resources in the given Object-Workscope combination.
The system displays the following field:
ES |
Indicates the status of the estimation of resources for the tasks which could be any of the following:
|
The system displays the following field:
QS |
Indicates the status of the quote of resources for the task, which could be either of the following:
|
Enter the following fields in the multiline:
Task # |
The number identifying the task for which resource estimation is done. Mandatory. Help facility available |
Enter the following fields in the multiline:
Task Seq. # |
The number identifying the sequence of the task for which resource estimation is to be done. |
Res. Type |
Use the drop-down list box to specify the type of resource for which estimation is to be done. The system lists the following options:
|
Res. Nos. |
The required number of resources as per the Task master. Mandatory. Search facility available. |
Time UOM |
Use the drop-down list box to specify the unit of measurement for the resource to be estimated. Mandatory. The system lists the following option:
By default the system leaves this field blank. |
The system displays the following field:
Reqd. Qty |
Indicates the required quantity of resources as in the Task master. |
NR Qty – Act. |
Indicates the non-routine number of resources for given combination of 'Object-Work scope' and 'Task - Part' combination. |
Enter the following fields “Est. Qty” group:
Reg. |
Quantity of resource hours which is required for estimation on a regular basis Ensure that the value entered in this field is a positive integer greater than 0. |
Non-Rtn |
Quantity of resource hours that is not planned for regular basis but as non-routines based on consumption history, which is required for estimation. Ensure that the value entered in this field is a positive integer greater than 0. |
The system displays the following field in the “Est. Qty” group:
Total |
The total estimated quantity. Regular - Est. Qty + Non Routine - Est. Qty |
The system displays the following field:
Reqd. Nos |
Indicates the count of resources required to perform the task from task master. |
Enter the following fields:
Est. Nos |
Indicates the estimated count of resources to perform the tasks, |
Attendance Type |
Use the drop-down list box the type of attendance for the resource for which estimation is to be done. Mandatory.
By default the system leaves this field blank. |
Cost / Unit |
The cost per unit of resources for the given 'Object-Workscope' combination. |
The system displays the following fields in the “Total Cost” group:
Reg. |
Regular - Est. Qty * Cost per Unit * Est. Nos |
Non Rtn. |
Non Routine - Est. Qty * Cost per unit *Est. Nos' |
Total |
Regular - Total Cost + Non Routine - Total Cost |
Enter the following fields:
Exclude? |
Use the drop-down list box to
|
Base Rate / Unit |
Indicates Base Rate per unit of resources for the given 'Object-Workscope' combination |
Enter the following fields in the “Markup / Unit” group:
Percentage |
Any markup that needs to be added against Base Rate/Unit can be specified as percentage. Ensure that the value entered in this field ranges from 0 to 100. |
Value |
Base Rate/Unit * (Mark up % / 100)' |
The system displays the following field:
Price / Unit |
Base Rate/Unit + Mark-up Value' |
The system displays the following fields in the “Extd. Base Price - Inclusions” group:
Reg. |
Regular - Est. Qty * Base Rate/Unit * Est. Nos. |
Non Rtn. |
Non Routine - Est. Qty * Base Rate/Unit * Est. Nos |
Total |
Regular - Extd. Base Price + Non Routine - Extd. Base Price |
The system displays the following fields in the “Extd. Mark Up - Inclusions” group:
Reg. |
Regular - Est. Qty * Mark-up Value * Est. Nos |
Non Rtn. |
Non Routine - Est. Qty * Mark-up Value * Est. Nos. |
Total |
Regular - Extd. Mark-up + Non Routine - Extd. Mark-up |
The system displays the following fields in the “Extd. Price - Inclusions” group:
Reg. |
Regular - Est. Qty * Price per unit * Est. Nos. (or) 'Regular - Extd. base Price + Regular - Extd. Mark-up |
Non Rtn. |
Non Routine - Est. Qty * Price per unit * Est. Nos' (or) 'Non Routine - Extd. base Price + Non Routine - Extd. Mark-up |
Total |
Regular - Extd. Price Inclusions + Non Routine - Extd. Price Inclusions |
The system displays the following fields in the “Total Cost - Inclusions” group:
Reg. |
Regular - Total Cost' from Resources multiline, if Exclude is not set as 'Regular' or 'Both' |
Non Rtn. |
Non Routine - Total Cost' from Resources multiline, if Exclude is not set as 'Non-routine' or 'Both' |
Total |
Regular - Total Cost Inclusions + Non-Routines - Total Cost Inclusions |
The system displays the following fields in the “Profit / (Loss) - Inclusions” group:
Reg. |
(Regular - Extd. Price Inclusions) - (Regular - Total Cost Inclusions)' |
Non Rtn. |
(Non Routine - Extd. Price Inclusions) - (Non Routine - Total Cost Inclusions) |
Total |
(Total - Extd. Price Inclusions) - (Total - Total Cost Inclusions) |
Enter the following fields in the “Markup / Unit” group:
Est. Remarks |
Any comment pertaining to the resources estimations. |
Qt. Working Remarks |
Any comment pertaining to the price workings of resources. |
The system displays the following fields in the “Exclusions” group:
Price |
Sum of all Extd. Price in both Regular as well as Non Routines whichever are excluded' |
Cost |
'Sum of all Total Cost in both Regular as well as Non Routines whichever are excluded' |
Profit |
'(Price-Exclusions) - (Cost-Exclusions) |
Enter the following fields:
Est. Notes |
A textual comment on the resource estimations. |
Qr. Working Notes |
A brief textual note on the Quote Working document. |
The system displays the following fields:
Task Desc. |
A brief textual note on the task that is added. |
Res. Desc. |
A brief description of the resources specified as defined in the Task master. |
Enter the following fields:
Est. Mod Notes |
Any textual comments on the modifications made to the estimations. |
Doc. Mod Notes |
A textual note on the modifications made in the Quote Working document. |
The system displays the following fields:
Base Rate SPL Curr. |
If any service pricelist is used to define the base rate/unit for resources, then display the corresponding currency of part from that pricelist. |
The system displays the following fields in the “Cost Summary” section:
Note: The system displays this section only if the login user is in Planner role.
Regular |
Cost: Displays the added value of 'Regular' column under the 'Total Cost' column grouping for all the tasks lines, for the given 'Object-Workscope-Pricing Model' combination |
Non-Routines |
Cost: Displays the added value of 'Non Routine' column under the 'Total Cost' column grouping for all the tasks lines, for the given 'Object- Workscope -Pricing Model' combination |
Total |
Cost: Displays the added value of 'Total' column under the 'Total Cost' column grouping for all the tasks lines, for the given 'Object- Workscope -Pricing Model' combination |
The system displays the following fields in the “Summary” sectio:
Note: The system displays this section only if the login user is in Commercial role.
Regular |
Cost: Displays the added values of adding 'Regular' column under the 'Total Cost Inclusions' column grouping for all the tasks line items, for the given 'Object- Workscope -Pricing Model' combination Price: Displays the added values of 'Regular' column under the 'Extd. Price Inclusions' column grouping for all the task line items, for the given 'Object- Workscope -Pricing Model' combination |
Non-Routine |
Cost: Displays the added values of “Non-Routine' column under the 'Total Cost Inclusions' column grouping for all the task line items, for the given 'Object- Workscope -Pricing Model' combination Price: Displays the added values of “Non-Routine' column under the 'Extd. Price Inclusions' column grouping for all the task line items, for the given 'Object- Workscope -Pricing Model' combination |
Total |
Cost: Display the added values of 'Total' column under the 'Total Cost Inclusions' column grouping for all the task line items, for the given 'Object- Workscope -Pricing Model' combination Price: Displays the added values of 'Total' column under the 'Extd. Price Inclusions' column grouping for all the task line items, for the given 'Object- Workscope -Pricing Model' combination. |
Click the “Get Requirements” pushbutton to retrieve resource requirements from the Task master.
Note: Ensure that at least one record in the multiline is selected.
Click the “Get NR Actuals” pushbutton to retrieve details of all the 'Routines' and 'Non-Routines from previous history'
Note: Ensure that at least one record is selected on the multiline.
Click the “Compute” pushbutton to re-run the computation logic for all the columns in the Resources multiline.
Click the “Save Resource Estimates” pushbutton to retrieve and update all the estimations made.
Click the “Save Resource Pricing” pushbutton to save pricing against the resources.
Note that for both Planner and Commercial Roles ensure that estimates is Completed and Confirmed against a task.
This section enables you to record estimates and price workings for charges against a Quote Working Document, which will then be considered for computing the final fixed price.
Enter the following fields in the “Charge Details” section:
Task # |
The number identifying the task for which charges estimation is done. Mandatory. Help facility available |
Task Seq. # |
The number identifying the sequence of the task for which charges estimation is to be done. |
Charge Code |
The code identifying the charges applied against a Task #.
Help facility available |
The system displays the following fields in the “Charge Details” multiline:
Charge Desc. |
A textual note on the corresponding charge code. |
Enter the following fields in the “Charge Details” section:
Variant Code |
The code identifying the variance of the corresponding charge code that is applied against a Task #. Help facility available |
The system displays the following fields in the “Charge Details” multiline:
Variant Desc. |
A textual note on the corresponding variant code. |
Enter the following fields in the “Charge Details” section:
Amount |
The amount charged against the task for the corresponding Charge Code |
Enter the following fields in the “Markup” section:
Percentage |
The Markup % to be added on the Charge amount. |
Value |
The Mark-up value added to the Charge amount calculated based on applying the Markup % on the amount. |
The system displays the following fields in the “Charge Details” multiline:
Total Value |
It displays the total value of the Charge applied against the task calculated as Amount + Mark-Up value. |
Note: Only the Charge Codes with Flat Basis Charge Type can be applied against a Task # in this tab.
The system displays the following fields in the “Summary” section:
Note: The system displays only ‘Cost’ in this section only if the login user is in Planner role
It displays Cost, Markup and Value if the login user is mapped to a commercial role..
Cost |
The sum of all the amount charged for the task for the given object-work scope combination. |
Markup |
The sum of all the markup values added to the Charge amount for the object-work scope combination. |
Value |
The sum of all the charges applied against the task for the object-work scope combination. |
Select the “Save Charges Pricing” pushbutton.
This tab enables you to have the visibility of Cost and Price Summary separately at Task / Material / Resources / Charges level for an ‘Object-Workscope-Pricing Model' combination. In this tab, you can to review the cost/Prices in the screen
! Note: The system does not display this tab for login user who is a Planner.
The system displays the following in the “Overall Price Summary” section:
Computed Price |
Indicates the total computed price workings for a given Object-Workscope-Pricing Model combination. The system displays the following:
|
Total Cost |
Indicates the total cost for a given Object-Workscope-Pricing Model combination. The system displays the following:
|
Profit |
Indicates the total profit for all the Object-Workscope-Pricing Model combination. The system displays the following:
|
Enter the following fields in the “Objectwise Summary” section:
Object – Workscope Pricing Model |
The Tree grid displayed as follows: Parent node – The Object Child node – Workscope – Pricing Model combination under the Object
|
The system displays the following in the “Computed Price – Inclusions” group if the parameter 'Consider Task. Prob Rate for Price Computation for Quote Working?' is set at any option other than ‘No’:
Materials |
Sum of values in Column 'Materials' under 'Adj. Computed Price Inclusions in Workscope multiline |
Resources |
Sum of values in Column 'Resources' under 'Adj. Computed Price Inclusions' in Workscope multiline |
Charges |
Sum of values in Column 'Charges' under 'Adj. Computed Price Inclusions’ in Workscope multiline |
Task Lvl. NRs |
Sum of values in Column 'Task Level. NRs' under 'Adj. Computed Price Inclusions’ in Workscope multiline |
Object Lvl. NRs |
Object Level Non- Routine Price defined for that Object-Workscope-Pricing Model combination |
Total |
Sum of Materials, Resources, Charges, Task Lvl. NRs and Object Lvl. NRs under this column grouping |
The system displays the following in the “Computed Price – Inclusions” group if the parameter 'Consider Task. Prob Rate for Price Computation for Quote Working?' is set as 'No':
Materials |
Sum of values in Column 'Materials' under 'Computed Price Inclusions’ in Workscope Multiline |
Resources |
Sum of values in Column 'Resources' under 'Computed Price Inclusions’ in Workscope Multiline |
Charges |
Sum of values in Column 'Charges' under 'Computed Price Inclusions’ in Workscope Multiline |
Task Lvl. NRs |
Sum of values in Column 'Task Level. NRs' under 'Computed Price Inclusions’ in Workscope Multiline |
Object Lvl. NRs |
Object Level Non- Routine Price defined for that Object-Workscope-Pricing Model combination |
Total |
Sum of Materials, Resources, Charges, Task Lvl. NRs and Object Lvl. NRs under this column grouping |
The system displays the following in the “Total Cost – Inclusions” group if the parameter 'Consider Task. Prob Rate for Price Computation for Quote Working?' is set at any other option other than ‘No’:
Materials |
Sum of values in Column 'Materials' under 'Adj. Cost Inclusions’ in Workscope Multiline |
Resources |
Sum of values in Column 'Resources' under 'Adj. Cost Inclusions’ in Workscope Multiline |
Charges |
Sum of values in Column 'Charges' under 'Adj. Cost Inclusions’ in Workscope Multiline |
Task Lvl. NRs |
Sum of values in Column 'Task Level. NRs' under 'Adj. Cost Inclusions’ in Workscope Multiline |
Object Lvl. NRs |
Object Level Non- Routine Cost defined for that Object-Workscope-Pricing Model combination |
Total |
Sum of Materials, Resources, Charges, Task Lvl. NRs and Object Lvl. NRs under this column grouping |
The system displays the following in the “Total Cost – Inclusions” group if the parameter 'Consider Task. Prob Rate for Price Computation for Quote Working?' is set as 'No':
Materials |
Sum of values in Column 'Materials' under 'Total Cost Inclusions’ in Workscope Multiline |
Resources |
'Sum of values in Column 'Resources' under 'Total Cost Inclusions’ in Workscope Multiline |
Charges |
Sum of values in Column 'Charges’ under ‘Total Cost Inclusions’ in Workscope Multiline |
Task Lvl. NRs |
Sum of values in Column 'Task Level. NRs’ under ‘Total Cost Inclusions’ in Workscope Multiline |
Object Lvl. NRs |
Object Level Non- Routine Cost defined for that Object-Workscope-Pricing Model combination |
Total |
Sum of Materials, Resources, Charges, Task Lvl. NRs and Object Lvl. NRs under this column grouping |
The system displays the following in the “Profit / Loss” - Inclusions” group if the parameter 'Consider Task. Prob Rate for Price Computation for Quote Working?' is set any other option other than ‘No’:
Materials |
Sum of values in Column 'Materials' under 'Adj. Profit / (Loss) Inclusions’ in Workscope Multiline |
Resources |
'Sum of values in Column 'Resources' under 'Adj. Profit / (Loss) Inclusions’ in Workscope Multiline |
Charges |
Sum of values in Column ‘Charges’ under 'Adj. Profit / (Loss) Inclusions’ in Workscope Multiline |
Task Lvl. NRs |
Sum of values in Column “Task Lvl. NRs’ under 'Adj. Profit / (Loss) Inclusions’ in Workscope Multiline |
Object Lvl. NRs |
Value in Obj. Level NRs in Computed Price Inclusions - Value in Obj. Level NRs in Total Cost Inclusions |
Total |
Sum of Materials, Resources, Charges, Task Lvl. NRs and Object Lvl. NRs under this column grouping |
The system displays the following in the “Profit / Loss” - Inclusions” group if the parameter 'Consider Task. Prob Rate for Price Computation for Quote Working?' is set as 'No':
Materials |
Sum of values in Column 'Materials' under 'Profit / (Loss) Inclusions’ in Workscope Multiline |
Resources |
Sum of values in Column 'Resources' under 'Profit / (Loss) Inclusions’ in Workscope Multiline |
Charges |
Sum of values in Column 'Charges' under 'Profit / (Loss) Inclusions’ in Workscope Multiline |
Task Lvl. NRs |
Sum of values in Column ‘Task Lvl. NRs’ under 'Profit / (Loss) Inclusions’ in Workscope Multiline |
Object Lvl. NRs |
Value in Obj. Level NRs in Computed Price Inclusions - Value in Obj. Level NRs in Total Cost Inclusions |
Total |
Sum of Materials, Resources, Charges, Task Lvl. NRs and Object Lvl. NRs under this column grouping |
Enter the following fields in the “Objectwise Summary” section:
FP Defn. For |
Use the drop-down list box to select the Fixed price definition. The system lists the following options: (Mandatory) · Labour · Material · Other Resources · Tasks By default the system leaves this field blank. |
Incl. Pricing Basis |
Use the drop-down list box to inclusion pricing basis. Mandatory. · Fixed Price by WU' By default the system leaves this field blank. |
Enter the following fields in the “Final Price” group::
Materials |
Total Value for Materials to be updated as Final price |
Others |
Total Value for Others to be updated as Final price |
Resources |
Total Value for Resources to be updated as Final price |
Total |
Total Value for ‘Object-Workscope-Pricing Model’ combination to be updated as Final price |
The system displays the following in the “Exclusions” group:
Price |
Sum of values in Column 'Total Price' under 'Exclusions' in Workscope Multiline |
Cost |
Sum of values in Column 'Total Cost' under 'Exclusions’ in Workscope Multiline |
Profit / Loss |
'Sum of values in Column 'Profit / (Loss)' under 'Exclusions’ in Workscope Multiline |
The system displays the following in the “Final Profit” group:
Materials |
Indicates the profit of materials based on difference between Material columns under Final Price and Computed price Inclusion sections. |
Resources |
The Final Profit of Resources based on difference between Resource columns under Final Price and Computed price Inclusion sections |
Total |
The Total Final Profit based on the difference between Total columns under Final Price and Computed Price sections. |
Others |
Indicates the final profit of others based on difference between other columns under final price and computed price Inclusion sections. Note that this field includes Sum of charges, Task Level NRs, Obj. Level NRs. |
Note: Ensure that at least one record in the multiline is selected.
Click the “Save” pushbutton. The system sums up the values entered in 'Materials', 'Resources' and 'Others' column under the Final price column grouping and displays in the 'Total' column under Final Price column grouping in Object Wise Summary Multiline.
Click the “Confirm Working” pushbutton to confirm the Quote Working document. Note: Ensure that the on Confirm working the Quote Working document is in status other than Confirmed, Cancelled or Revised.
Click the “Update FP to Ref. Doc” pushbutton to update the price workings of Object-Workscope-Pricing Model combination from quote working document to its corresponding reference document (i.e.) Bid Contract.
Note: Ensure that the Quote Working document is in Confirmed status only if you wish to update FP to Ref. Doc.