MRP Run Review

MRP Run Review - A summary of the activity

Unified Glossary

Basics of using a a typical web page

Using Online Help

The “MRP Run Review” page appears.

Enter the following fields in the header section:

Planning By

Use the drop-down list box to specify the level at which the MRP Run is to be reviewed. The system lists the values “OU Level” and “Part Group Level”.

 

Use the drop-down list box to select the part/service group for which the MRP Run is to be reviewed. The system lists all the part/service groups created with the purpose as Material Requirement Planning in the Create part / service groups activity of the “Part Administration” business component.

Note: This field appears only if the “Set Option” field is selected as ‘Part Group Level’.

The system displays the following fields in the header section:

Horizon

The starting date from which MRP Run is to be reviewed which is the created date of the value ‘Planning Horizon’ in “MRP Process Parameters” screen.

Example: In “MRP Process Parameters” screen, if the value "Planning Horizon" has created date as "19-01-2021" then that date is displayed.

 

The ending date upto which the MRP Run is to be reviewed which is derived from the ‘Planning Horizon’ and ‘Planning Horizon UOM’ values in “MRP Process Parameters” screen.

Example: If the value Planning Horizon is given as "2" and UOM as "months" then the system displays the "to date" as the date from 2 months of the "from date".

 

The duration for which the MRP Run is to be reviewed.

Example: 2 Months

Search By

The Part #/Part Description/Part Category/Part Type for which the MRP details are to be retrieved in the multiline.

Exception Type

Use the drop-down list box to specify the exception type. The system lists the following values:

  • Deficit - Parts that are Deficit will be displayed in the Horizon Summary and Slot Wise Summary Multiline.

  • Surplus - Parts that are Surplus will be displayed in the Horizon Summary and Slot Wise Summary Multiline.

  • Equilibrium - Parts for which demand and supply matched exactly will be displayed in the Horizon Summary and Slot Wise Summary Multiline.

  • Exception Messages - Parts with "Message" column having values in "To be Planned" Tile of "Material Plan" screen will be displayed in the Horizon Summary and Slot Wise Screen

  • Manual Action - Parts that are surplus and have value as ‘zero’ in “Action” field will be displayed in the Horizon Summary and Slot Wise Summary Multiline.

MRP Run Details

The system displays the following fields in the header section of the “MRP Run Details” section.

Line #

The row # of the part # selected.

Part #

The number identifying the part.

Part Description

The description of the part.

Safety Stock

The value in safety stock of the part defined in the “maintain planning information” screen and the concatenation of its UOM.

Source

The Part source of the part defined in the “MRP Action Parameters” screen which could be “Make”, “Purchase” or “Make & purchase”.

Lead Time

The lead time of the part which could be one of the following:

§   Purchase Lead Time if the part source is purchase.

§   Make Lead Time if the part source is make.

Part wise Demand and Supply break up

This multiline displays the breakup of demand and supply for aggregated horizon UOM (on Part # selection). The following are the categories for which the breakup is displayed:

Graph View

The graph section displays the following graphs with the X-axis as aggregated horizon UOM and Y- axis as quantity: