Entering resources/sign-off information for the task
This page allows you to add or modify the resource/sign-off details required for executing the task. Tell me more
Select the “Edit Resource/Sign-Off Requirement” link at the bottom of the main page.
The “Edit Resource/Sign-Off Requirements” page appears.
The system displays the following fields in the “Task Details” group box:
Task Applicability |
Indicates whether the task is applicable for “Aircraft”, “Engine” or “Component”. |
Base Aircraft Model # |
The number identifying the base aircraft model on which the task can be performed |
Task # |
The task for which the resource details have to be specified. |
Revision # |
The revision number of the task for which the resource details have to be specified. |
Task Description |
The textual description of the task. |
Enter the following in the “Resource Details” group box:
Resource Type |
Use the drop-down list box to select the type of the resource for which the details are to be added or modified. The available options are “Tools”, “Others”, “Skills”, and “Equipment”. The system sets the field to “Skills” by default. |
Click the “Get details” pushbutton to retrieve the resource details that are already defined for the task and resource type combination.
Enter the following field:
Update based on Actuals |
Check this box if you wish to update the resource details based on the actual details of resources consumed during execution of the task. |
Enter the following fields to modify these details or add new resources for the task in the “Resource Details” multiline:
Resource # |
The resource required for completing the task (Alphanumeric, 40). The resource of type “Skills” must have been defined in the "Create Employee File" activity of "Employee Information" business component and resource of type “Tools”, “Others” and “Equipment” must have been defined in the “Work Center” business component. For each resource type, the resource number must be unique within the multiline. Help facility available. |
The system fills in the following field on clicking the “Edit Resources” pushbutton:
Resource Description |
The textual description of the resource. |
Enter the following fields:
Customer # |
The customer # for the resource. Help facility available. |
Time Unit |
Use the drop-down list box to specify the unit of measurement for the resource time, which could be “Minutes”, “Hours” or “Days”. The system sets the field to “Hours” by default. |
Est. Time |
The number of hours, minutes or days for which the resource is required to complete the task (Decimal). Mandatory. For “skill” type resources, if the sum of estimated duration, in terms of hours, is greater than the total man-hours estimated for the task, the system automatically sets the estimated man-hours to the sum of the estimated duration entered in the multiline. |
Est. Nos. |
The number of resources required for completing the task (Integer). Ensure that the value entered in this field is positive. |
Approval Reqd.? |
Use the drop-down list box to indicate whether the resource should be an approved resource or not. The available options are Yes” and “No” and the system displays “No” by default. |
Sign-Off? |
Use the drop-down list box to indicate whether the user has to sign after the task has been carried out by the resource. The options available are “Yes” and “No”.The system displays "Yes" by default. This field is applicable only for “skill” type resources. |
Allow Alternates? |
Use the drop-down list box to confirm whether the task can be signed off by a mechanic with an alternate skill instead of the primary skill. Select:
By default, the drop-down list box is set as No. |
Check the box in the multiline to mark the resource for deletion.
Click the Delete icon in the tool bar above the multiline, to delete the resources selected in the multiline.
Click the "Edit Resources" pushbutton to add or modify the details of the resource
Note: This action is workflow-enabled. Notification messages can be sent and you can configure further processing of this document in the "Workflow Management" business component.
The system performs the following:
In the case of modifying the resource requirement details of a “Returned” task, the system changes the status of the task to “Fresh” status. The status log is also updated.
If a new resource of type “Skills” is mapped to the task, the system copies the corresponding sub-task details to the resource number, if the “Sign-Off?” flag is set as “Yes”.
Indicate the following under the Task Sign-Off Information group box:
RII Sign-Off Required? |
Use the drop-down list box to select:
|
The system displays the following field in the “Sub-Task Sign-Off Information” group box:
Resource Type |
The type of the resource, which could be “Tools”, “Others”, “Skills” or “Equipment”. The system displays “Skills” by default. |
Enter the following field in the “Sub-Task Sign-Off Information” group box:
Resource # |
Use the drop-down list box to specify the resource required for completing the task. The system lists all the resources specified in the “Resource Details” multiline, for which “Resource Type” is “Skills” and “Sign-Off?” flag is set as “Yes”. |
Note: If resources are deleted in the “Resource Details” multiline, the system automatically removes the corresponding resources from the “Resource #” drop-down list box.
Click the “Get details” pushbutton provided alongside to retrieve the sub-task details for the task number, aircraft model number and resource number combination.
The system displays the following fields in the “Sub-Task Sign-Off Information” multiline, on clicking the “Get Details” pushbutton:
The system lists all the sub-tasks of the resources for which the “Sign-Off? flag is set as “Yes” in the “Resource Details” multiline.
Seq # |
The sequence in which the sub task should be performed, while executing the maintenance task. |
Sub Tasks |
The sub task that has to be performed while executing the maintenance task. |
Enter the following field:
Resource Group |
Use the drop-down list box to specify the resource group. The system lists the options “Not Required”, “Mechanic”, “Inspector” and “Insp & Mech”. |
Note: You can set the “Resource Group” only to “Inspector” or “Not Required”, if the resource group of the sub-task is set as “Inspector” in the previous page.
You can set the “Resource Group” only to “Mechanic” or “Not Required”, if the resource group of the sub-task is set as “Mechanic” in the previous page.
Note: If resources are deleted in the “Resource Details” multiline, the system automatically removes the corresponding sub-task details from the multiline.
Click the "Edit Sign-Off Details" pushbutton to update the sign-off details.
The system updates the sub tasks and corresponding resource group against the task number and aircraft model number combination.
Entering resource/sign-off information for the task – An overview
This option allows you to add or modify the details of resources required for executing the task. If you wish to define the resources for the task, you can enter details such as resource code, estimated duration, and number of resources needed against each resource type. You can also indicate whether the resource should be an approved resource or not and whether sign off is required for the “Skill” type resource. Based on this information during work reporting sign off sheet will be automatically generated by the system. You can also retrieve resources that have already been defined for the task and modify its details.
This page also allows you to update the sign-off details pertaining to the task. You can also assign the tasks and sub tasks to resource groups in this page.
The system updates the resource/sign-off details and sets the last modified date to the current server date.
Update the resource with the actual parts consumed
Select resource type required for task
Update the resource with the actual parts consumed
You can indicate, whether the resource details has to be updated based on the actual details of resource consumed during the execution of task.
Check the “Update based on Actuals” box to update the resources with the actual resources consumed.
Select resource type required for task
You can specify the resource required for completing the task.
Set the “Resource Type’ drop-down list box to “Skill” to add skill type resource to task.
Set the “Resource Type’ drop-down list box to “Tools” to add the tools required for task.
Set the “Resource Type’ drop-down list box to “Equipment” to add the equipment required for task.
Set the “Resource Type’ drop-down list box to “Others” to add other type of resource required for task.