Employee Costs – Plan Updation
Select the “Employee Costs – Plan Updation” activity under the “Cost Revenue Plan” business component.
The “Employee Costs – Plan Updation” page appears.
-
Clicking this icon available near certain fields takes you to the help
page of the respective field.
Note: Employee Cost – Initial Plan must be created already in order to create the plan updation.
Enter the following in the header:
Project Code |
The code identifying the project Mandatory. |
The system displays the following from the Initial plan of the project on entering the project code:
Project Name |
The name of the project. |
Currency |
The currency of the project. |
Onsite Company |
The onsite company of the project. |
The system displays the following:
Version No. |
The version number of the project. The system fetches and defaults 1 as the Version number if the plan updation is made for the first time for the project. |
Residual From |
The date from which the plan updation for the project is applicable. |
Enter the following:
To |
The date till which the plan updation for the project is valid. |
The system displays the following:
Actual Calculated Upto |
The actual date up to which the Salary Cost Allocation Engine has been run for the project. |
The system displays the following in the “Onsite (Efforts per Person Months)” multiline:
Grade |
The system fetches the grades for which either plan has been set or actual efforts have been recorded in the On-Site ML of the Initial plan for the project. |
Residual Efforts |
The required residual effort. |
Proposed Residual Efforts |
The proposed residual effort. |
Total Efforts – Previous Plan |
The total effort as per the previous plan. |
Total Efforts - Actual |
The actual total effort. The system fetches the actual efforts of all the employees corresponding to the Grades and Project code from the Timesheet and displays against each grade appropriately. |
Enter the following:
Efficiency Factor |
The efficiency factor of the employee. Mandatory. The efficiency factor should be between 1 and 100. |
Residual Efforts |
The required residual effort. Mandatory. |
Click the “Compute Employee Cost” pushbutton to compute the Onsite employee cost required for the project.
The system displays the following:
Residual Employee Cost |
The Onsite residual employee cost.
|
Actual Efforts |
The actual efforts. |
Total Efforts |
The total efforts. |
Actual Employee Cost |
The actual Onsite employee cost as per the Initial plan for the project. |
Total Employee Cost |
The total employee cost. |
The system displays the following in the “Off-Shore” multiline:
Grade |
The system fetches the grades for which either plan has been set or actual efforts have been recorded in the Off Shore ML of the Initial plan for the project. |
Residual Efforts |
The required residual effort. |
Proposed Residual Efforts |
The proposed residual effort. |
Total Efforts – Previous Plan |
The total effort as per the previous plan. |
Total Efforts - Actual |
The actual total effort. The system fetches the actual efforts of all the employees corresponding to the Grades and Project code from the Timesheet and displays against each grade appropriately. |
Enter the following:
Efficiency Factor |
The efficiency factor of the employee. Mandatory. The efficiency factor should be between 1 and 100. |
Residual Efforts |
The required residual effort. Mandatory. |
Click the “Compute Employee Cost” pushbutton to compute the offshore employee cost required for the project.
The system displays the following:
Residual Employee Cost |
The Offshore residual employee cost.
|
Actual Efforts |
The actual efforts. |
Total Efforts |
The total efforts. |
Actual Employee Cost |
The actual Offshore employee cost as per the Initial plan for the project. |
Total Employee Cost |
The total employee cost. |
Residual Infrastructure Cost |
The residual infrastructure cost. |
Actual Infrastructure Cost |
The actual infrastructure cost. |
Total Infrastructure Cost |
The total infrastructure cost. |
Click the “Save Draft” pushbutton to save the employee cost- updation plan in Draft status.
Click the “Save and Update Plan” pushbutton to save the employee cost- updation plan.
The system saves the details of the employee cost – updation plan successfully.
Click the “Print” pushbutton to print the details of the employee cost- updation plan.
The system displays the following in the Data History group box:
Created By |
The name of the user who created the employee cost plan. |
Created Date |
The date on which the employee cost plan was created. |
Last Modified By |
The name of the user who last modified the employee cost plan. |
Last Modified Date |
The date on which the employee cost plan was last modified. |