The popup displays the following information:
Progress bars
Elapsed Time |
The elapsed time for SWO # in Green. The % of Green in the progress bar is derived in the following way: § Total Elapsed Time = Planned End Date & Time - Planned Start Date & Time § Time passed as of now = Current System Date & Time - Planned Start Date & Time Remaining Time = Total Elapsed Time - Time passed as of now . |
Work Completion |
The work executed against the SWO # in Green. The % of Green in the progress bar is derived in the following way: § Total Elapsed Time = Total count of tasks + Total count of discrepancies § Work completed as of now = Total count of tasks in 'Completed' status + Total count of discrepancies in 'Closed' status Remaining work to be completed = Total Work Completion - Work completed as of now |
Worked Hours |
The sum total of hours clocked against all tasks and discrepancies SWO #. The % of Green in the progress bar is derived in the following way: § Total Worked Hours = Total estimated hours of tasks + Total estimated hours of discrepancies § Worked Hours as of now = Total time bookings done for tasks + Total time bookings done for discrepancies Remaining Work Hours = Total Worked Hours - Worked Hours as of now |
Cards Section
Exec. Doc. Hold? |
Indicates the Hold status of SWO #
|
Estimated? |
Indicates the Estimation status of SWO #
Note: This card will not be available, if Estimation is 'Not Required' and, if SWO # is not based on customer order |
Quoted? |
Indicates the Quotation status of SWO #
Note: This card will not be available, if Estimation is 'Not Required' and if SWO # is not based on customer order |
CO Hold? |
Indicates the Hold status of the customer order associated with SWO#
Note: This card will not be available, if SWO # is not based on customer order. |