Package creation process
On creation of a new package, the tasks that are pending for compliance on the aircraft, are automatically to the Package. This happens based on the attributes set in the “Edit Document Type Attributes” page of the “Common Masters” business component.
Incomplete Tasks
If the attribute “Auto Inclusion of Incomplete Tasks” is set as “Required”, the system does the following.
Copies the incomplete tasks with 'Actual Start Date & Time' earlier than the 'Planned Start Date & Time' of the package.
Copies all the part requirements, component removal details, resource requirements and parameter reading requirements of the task and also its 'Concurrent' related tasks.
Updates the 'Execution Status' of the task in the package as “Planned”.
Overdue tasks
If the attribute “Auto Inclusion of Overdue Tasks” is set as “Required”, the system performs the following:
Copies the tasks with 'Schedule Date' earlier than the Server Date, into the package.
Copies all the sub tasks, sign-off requirements, part requirements, component removal details, resource requirements and parameter reading requirements of the task and also its 'Concurrent' related tasks.
Due Tasks
For the attribute “Basis for Auto Inclusion of Due Tasks”, the system performs the following.
Copies the tasks with the 'Plan Date' equal to the Server Date, if the attribute is set as “Planned Start Date”.
Copies the tasks with the 'Schedule Date' equal to the Server Date, if the attribute is set as “Schedule Start Date”.
Copies the tasks with the 'Plan Start Date’ or ‘Schedule Date ' equal to the Server Date, if the attribute is set as “'Planned Start Date & Schedule Start Date”.
Copies all the sub tasks, sign-off requirements, part requirements, component removal details, resource requirements and parameter reading requirements of the task and also its 'Concurrent' related tasks.
Note: In all the cases mentioned above, tasks having ‘Conflict’ relationship among them will not be copied.
Tasks having ‘Predecessor Constrained’ relationship and that are not complied for the aircraft at least once will get added to the Package.