Consider that a Component Engine 'E1' has Component Replacement task identified as 'CR1'. For E1, Component Program exists with two tasks and Parent Removal is “Not Required”.

Tasks   Due Date

 T1          03-Sep

 T2          02-Sep

Say, ‘E2’ is the child component directly attached to ‘E1’ and Component Program exists with Parent Removal set as “NHA”.

Tasks    Due Date

  T3          04-Sep

 Say, ‘E3’ is attached to ‘E2’ and Component Program exists with Parent Removal set as “EIPN” (End Item Part Number).

Tasks    Due Date

  T4          01-Sep

Due Items in Aircraft Maintenance Execution are loaded in the following format:

CR1

 T4

 T2

 T1

 T3

Note: CR task must be displayed as folder header and if the user expands the CR task folder, all its Off-wing tasks must be displayed. According to the task due date