Update of computation basis controls - Post Compliance

The system updates the NSD / NSV computation basis controls ‘Next Due Calc. On’, ‘Calc. Ref. Date’ and ‘Last Schedule Date / Value’ in the “Edit Schedule Date/Value” page of the “Aircraft Maintenance Program” business component, based on the ‘Change Type’ selected and the value entered / modified by the user, as shown in the table below:

‘Change Type’ selected

User action

Next Due Calc. On

Calc. Ref. Value / Date

Last Schedule  Date / Value

Correction

If the user modifies NSV manually

Manual : Correction

Value entered by user

Last Due Value or Date and Time

Correction

If the user modifies Journey logs prior to compliance date, for a complied task having manually entered NSD / NSV

Time Window / Schedule / Actual Completion

Last Due Value / LPV

Last Due Value / LPV

Correction

If the user modifies LSV manually

Manual : Correction

Value entered by user

Last Due Value

Correction

If the user modifies Journey logs prior to compliance date, for a complied task having manually entered LSV

Time Window / Schedule / Actual Completion

Last Due Value / LPV

Last Due Value / LPV

Correction

If the user modifies LSV and NSV manually

Manual : Correction

Value entered by user

Last Due Value or Date and Time

Correction

If the user modifies Journey logs prior to compliance date, for a complied task having manually entered LSV and NSV

Time Window / Schedule / Actual Completion

Last Due Value / LPV

Last Due Value / LPV

Note: On modification of journey log, the system re-computes Next Schedule Value based on 'Update Basis, set for the last compliance.

Re-baseline

If the user modifies NSD / NSV manually

Manual : Re-baseline

Value entered by user

Last Due Value or Date and Time

Re-baseline

If the user modifies Journey logs prior to compliance date, for a complied task having manually entered NSV

Manual : Re-baseline

Value entered by user

Last Due Value

Re-baseline

If the user modifies LSD / LSV manually

Manual : Re-baseline

Value entered by user

Last Due Value or Date and Time

Re-baseline

If the user modifies Journey logs prior to compliance date, for a complied task having manually entered LSV

Manual : Re-baseline

Value entered by user

Last Due Value

Re-baseline

If the user modifies LSD / LSV and NSD / NSV manually

Manual : Re-baseline

Value entered by user

Last Due Value or Date and Time

Re-baseline

If the user modifies Journey logs prior to compliance date, for a complied task having manually entered LSV and NSV

Manual : Re-baseline

Value entered by user

Last Due Value

Note: The system will not re-compute Next Schedule Value, if 'Change Type' is set as "Re-baseline".