More details - Deferred Till date
For first time deferral
If the record status of the discrepancy # is updated to “Pending Deferral” or “Deferred”, the system calculates and updates the Deferral Till Date of the discrepancy, based on the logic mentioned in the below table.
The formulae in the table below are applicable if the discrepancy is deferred to exact time (i.e. if the process parameter “Next Due computation logic” is set as ‘Exact Date & Time’.
Discrepancy Deferred by |
‘Deferral Limit Basis for calendar day / flight day computation’ set for the selected Deferral Type in “Common Masters” business component |
Deferral Till Date |
Calendar Days |
Include Reporting Date |
Deferral Till Date / Time = Reported Date (Local) + Deferral Duration – 1 Day Convert Time to 23:59 ---> Convert Date/Time to UTC Time Zone and save |
Exclude Reporting Date |
Deferral Till Date / Time = Reported Date (Local)) + Deferral Duration Convert Time to 23:59 ---> Convert Date/Time to UTC Time Zone and save |
|
Not Applicable |
Deferral Till Date / Time = Reported Date / Time (UTC) + Deferral Duration |
|
Calendar Hours |
- |
Deferral Till Date / Time = Reported Date / Time (UTC) + Deferral Duration |
Calendar Months |
- |
Deferral Till Date / Time = Reported Date / Time (UTC) + Deferral Duration |
Flight Day |
Include Reporting Date |
Deferral Till Date / Time = Server Date (Local) + [(Param value as of Reporting Date with time set as 00:00 (Local) + Deferral Duration) - Current Param value] Convert Time to 23:59 ---> Convert Date/Time to UTC Time Zone and save |
Exclude Reporting Date |
Deferral Till Date / Time = Server Date (Local) + [(Param value as of Reporting Date with time set as 23:59 (Local) + Deferral Duration) - Current Param value] Convert Time to 23:59 ---> Convert Date/Time to UTC Time Zone and save |
|
Not Applicable |
Deferral Till Date / Time = Server Date (UTC) + [(Param value as of Reporting Date & Time (UTC) + Deferral Duration) - Current Param value] |
|
Other Params |
- |
Deferral Till Date / Time = Server Date (UTC) + [(Param value as of Reporting Date & Time in UTC + Deferral Duration) - Current Param value] / Avg Daily Utilization |
if the process parameter “Next Due computation logic” is set as ‘End of Day’, the formulae mentioned in the above table is applicable, except for the following:
Conversion of Date/Time to UTC Time Zone is not required.
Conversion of time to ‘23:59’ (without UTC conversion), is required for discrepancies deferred by ‘Calendar Months’ and ‘Other Params’ also.
For Repeat discrepancies
If the record status of the discrepancy # is updated to “Pending Deferral” or “Deferred” and if “Recurring?” is set as “Yes”, the system updates the Deferral Till Date / Time of the discrepancy # based on the following logic:
If deferral duration alone is given, the Deferral Till Date & Time = Discrepancy Execution Date + Deferral duration.
If FH is given, the Deferral Till Date & Time = [(Threshold Value-Current FH )/ Avg. Utilization Value of FH] + Discrepancy Execution Date
If FC is given, then Deferral Till Date & Time = (Threshold Value-Current FC )/ Avg. Utilization Value of FC) + Discrepancy Execution Date
If any one of the consumption parameter other than FH, FC and Calendar, the Deferral Till Date & Time = Discrepancy Execution Date + (the parameter value as on the discrepancy reported date / Average utilization value for the parameter)
If both FH & FC are available, the Deferral Till Date is calculated separately for FH and FC and the earliest / latest date (based on the Deferral Limit Basis set) is updated as Deferral Till Date & Time.
If both calendar based date and user based FH and FC or any other usage-based parameters are available, the Deferral Till Date is calculated individually for the deferral duration, FH, FC, and for the other parameters as per the logic above, and the earliest / latest date (based on the limit basis set) is updated as the Deferred Till Date & Time.
Note: The above formulae holds good if the process parameter “Next Due computation logic” is set as “Exact Date & Time”. If the process parameter is set as ‘End of Day’, conversion of time to’23:59’ is done.
The system considers the Execution Date & Time of the discrepancy as the ‘Reference Date & Time’ for the Repeat Scenario.
The ‘Deferral Limit Basis’ option is not considered if the “Recurring?” drop-down list box is selected as “Yes”.