More details-Threshold date

At the onset the system derives the following for generation of Threshold Date:

For example, discrepancy 1 was reported on 12/01/2009 with Deferral Limit Basis set as "Include Reporting Date" and Deferral Duration of 10 days:

Threshold Date = Reference Date + Deferral Duration

12/10/2009 = 12/01/2009 + 10 days

Conversely, if the option Deferral Limit Basis is set as "Exclude Reporting Date", the Reference date will be the Reported Date of the discrepancy + 1 day.

Considering the previous example but with the Deferral Limit Basis as "Exclude Reporting Date" :

Threshold Date = (Reference Date + 1 day) + Deferral Duration

12/11/2009 = (12/01/2009 + 1 day) + 10 days