Viewing resource actuals information for CWO

View Work Execution Details - A summary of the activity

Unified Glossary

Basics of using a typical web page

Using Online Help

In this page, you can view the resource actuals reported against a task or component work order. You can specify the task for which you need to view the resource actuals. The system displays the resource actuals, such as the resource code, type, description, actual hours for which the resource is utilized for the selected task. If the task number is not specified, the system displays the resource actuals reported directly against the component work order.

The “View Resource Actuals Information” page appears.

The system displays the following:

Date & Time Format

The format in which the date and time fields are displayed in this page. This format is displayed from the "User Preferences" business component based on the login user ID. In case the format is not defined, the system displays the date and time format from the "Enterprise Modeling" business component by default.

The system displays the following in the “CWO Details” group box:

Comp. Work Order #

The component work order selected in the “Select Component Work Order” page.

Component #

The number that identifies the component on which the component work order has been generated.

CWO Description

The textual description of the component work order.

Zoom facility available.

CWO Status

The status of the component work order, which could be “Scheduled”, “Inprogress”, “Completed”, "Pre-closed" or "Closed".

Part #

The part number of the component on which the component work order has been generated.

Serial #

The serial number of the component on which the component work order has been generated.

Task #

Use the drop-down list box to select the task for which you need to view the resource actuals details. The system displays the numbers (along with the sequence number) of all the tasks within the selected component work order. The system sets the task number selected in the “View CWO Execution Information” page by default.

The system displays the following:

Task Status

The status of the selected task within the component work order, which could be “Scheduled”, “In-Progress”, “Completed”, or “Closed”.

Note: If no task number is selected in the “View CWO Execution Information” page, then the system sets the field blank by default.

Task Description

The textual description of the selected task.

Zoom facility available.

Work Center #

The work center to which the selected task or component work order is assigned.

Note: The system displays the resource actuals of the selected task. If no task is selected, the system displays the resource actuals of the corresponding component work order.

The system displays the following in the “Resource Details” multiline:

Resource #

The number that identifies the essential resources required to execute the task or component work order.

Facility Object #

The number identifying the facility object used to execute maintenance jobs on aircraft or aircraft-related components.

Resource Type

The resource type, which is required to execute the task.

Resource Description

The textual description of the resource.

Signed Off?

The system displays “Yes” or “No” to indicate whether the resource has performed signoff for the task or component work order.

Used Duration

The duration of time for which the resource is utilized.

Assigned Hours

The scheduled number of hours for which the resource is assigned to the task or component work order.

From Date

The start date, in the specified date format, from which the resource is assigned to the task or component work order.

From Time

The start time, in the specified time format, from which the resource is assigned to the task or component work order.

To Date

The end date, in the specified date format, till which the resource is assigned to the task or component work order.

To Time

The end time, in the specified time format, till which the resource is assigned to the task or component work order.

Attendance Type

The attendance type of the resource, such as holiday, overtime, and normal, while executing the task.

Comments

Additional remarks pertaining to the resource utilized for the task.