Viewing resources estimated for CWO
This page enables you to view the details of the resources estimated for carrying out the component work order and the tasks associated to it. Tell me more.
Select the “View Estimated Resources” link at the bottom of the “View Component Work Order Information” or the “View Resource Assignments” page.
The “View Resource Requirements” page appears.
The system displays the following details in the “CWO Details” group box:
Comp. Work Order # |
The component work order for which the estimated resource details are displayed. |
CWO Description |
The textual description of the component work order. Zoom facility available. |
Maintenance Type |
The maintenance type to which the component work order belongs. |
Work Center # |
The work center responsible for component work order execution. |
Part # |
The part number to which the component belongs. |
Serial # |
The serial number of the component against which the component work order is raised. |
Enter the following field:
Task # |
Use the drop-down list box to select the task for which the estimated resource details are displayed. The system lists all the tasks that are already associated to the component work order. The system displays the number as a combination of the task number and sequence number. |
Leave this field blank to view the resource details for the entire component work order. |
The system displays the following field:
Task Description |
The textual description of the task. Zoom facility available. |
Enter the following field:
Resource Type |
Use the drop-down list box to select the type of resource to which the resource belongs. The system lists the options “Skill”, “Equipment”, “Tools” and “Others” and sets the field to “Skill” by default. |
Click the “Get Details” pushbutton to retrieve the details.
The system displays the following details in the “Resource Details” group box:
Resource # |
The resource that is required for carrying out the task. |
Resource Type |
The type to which the resource belongs, which could be “Skill”, “Equipment”, “Tools” or “Others”. |
Resource Description |
The textual description of the resource. |
Time Unit |
The unit of measurement for the resource requirement time, which could be “Minutes”, “Hours” or “Days”. |
Est. Elapsed Time |
The number of hours, minutes or days for which the resource is required to complete the task. |
Est. Quantity |
The number of resources required for carrying out the maintenance task. |
Resource Cost |
The cost incurred on the resource estimated for the task. |
Sign Off? |
The system displays “Yes” or “No” to indicate whether the user has to sign after the task has been carried out by the resource. |
Viewing resources estimated for CWO – An overview
In this page, you can view the details of the resources estimated for carrying out the component work order as well as for the tasks associated to the component work order. The details of resources are already estimated in the “Create Component Work Order” activity.
You can select the task and resource type, which could be “Equipment”, “Skill”, “Tools” or “Others”, and view the resource details. Details such as resource code, time unit, estimated duration, the number of resources needed for the task or CWO execution and whether sign off is required or not, are displayed in the multiline. The details can be viewed either at the CWO level or at the task level.