If the “Compliance Updation Basis” is set as “Time Window” in the “Set Options” activity of the current business component, then the NSD will be calculated based on:

E.g., For the work unit the next due is on 10/05/07, repeat interval is 20 days and tolerance is +/- 3 days, if the work unit is executed on any date between 07/05/07 to 13/05/07 (both dates included), then the NSD is calculated as 30/05/07 (10/05/07 + 20 days = 30/05/07). If the work unit is executed on any date beyond the tolerance limits (07/05/07 to 13/05/07) and the work unit is executed on 05/05/07 or 14/05/07, then the NSD is calculated as on 25/05/07 and 03/06/07 respectively (Executed Date + 20 days).