Viewing reschedule history of a component work order
This page allows you to view the rescheduling history details of the CWO, which is not in the “Cancelled” status. Tell me more.
Select the “View CWO Reschedule History” link at the bottom of the “Select Component Work Order” page.
The “View CWO Reschedule History” page appears.
The system displays the following field:
Date Format |
The format in which the date field is displayed. This format is displayed from the "User Preferences" business component based on the login user id. In case the format is not defined, the system displays the date format from the "Enterprise Modeling" business component by default. |
The system displays the following details in the “CWO Details” group box:
Comp. Work Order # |
The component work order for which the rescheduling history details are displayed. |
Component # |
The component for which the component work order was generated. |
Part # |
The part number of the component against which the component work order is raised. |
Serial # |
The serial number of the component against which the component work order is raised. |
CWO Description |
The textual description of the component work order. Zoom facility available. |
CWO Status |
The status of the component work order. |
The system displays the following fields in the “Reschedule Details” multiline:
Comp. Work Order # |
The component work order for which the rescheduled details are displayed. |
Planned Start Date |
The date at which the component work order execution was planned to be started. |
Revised Start Date |
The revised date at which the component work order execution was started. |
Planned End Date |
The date at which the component work order execution was planned to be completed. |
Revised End Date |
The revised date at which the component work order execution was completed. |
Reschedule Count |
The number of times the component work order was rescheduled. |
Viewing reschedule history of a component work order– An overview
The component work order or the tasks associated to the CWO are rescheduled, due to unexpected delays or some changes in the planning. This page allows you to view the rescheduling history details of the CWO, which is not in the “Cancelled” status. You can view the planned start and end dates, latest revised start and end dates and the number of times the component work order was rescheduled.