Setting planned start and end dates
The Standard Work Calendar feature can be enabled / disabled as per the requirement of users. See Installation Manual for more details.
The data in the following table illustrates the reasoning used by the system to generate the planned start and end dates of a task. However, these dates are for display purposes only.
Task |
T1 |
Standard Work Calendar Timings |
09:00 Hrs to 17:00 Hrs |
Elapsed Time for the task |
15 Hrs |
Scheduled Start Date |
April 20 2009 |
Planned Start Date |
April 20 2009 |
Planned Start Time |
09:00 Hrs |
Planned End Date |
April 21 2009 |
Planned End Time |
16:00 Hrs |
Note: The elapsed time of 15 hrs for the task is distributed over two days - 8 Hrs on April 20 and 7 Hrs on April 21 considering the Standard Work Calendar Timings of 8 Hrs in a day.