Setting planned start and end dates

The Standard Work Calendar feature can be enabled / disabled as per the requirement of users. See Installation Manual for more details.

The data in the following table illustrates the reasoning used by the system to generate the planned start and end dates of a task. However, these dates are for display purposes only.

Task

T1

Standard Work Calendar Timings

09:00 Hrs to 17:00 Hrs

Elapsed Time for the task

15 Hrs

Scheduled Start Date

April 20 2009

Planned Start Date

April 20 2009

Planned Start Time

09:00 Hrs

Planned End Date

April 21 2009

Planned End Time

16:00 Hrs

Note: The elapsed time of 15 hrs for the task is distributed over two days - 8 Hrs on April 20 and 7 Hrs on April 21 considering the Standard Work Calendar Timings of 8 Hrs in a day.