Example:

Consider the tasks ‘T1’, ‘T2’ and ‘T3’ whose Repair Scheme details are given below:

Seq. #         Related Task #

10                            T1

Blank                       T2

20                            T3

On invoking ‘Re-Generate Seq #’, the sequence number is generated as follows (Assume ‘Re-Sequence Multiplication Factor’ is set as “5” for “All Packages” entity in Define Process Entities activity):

Step 1: Rep. Seq. # generation:

Seq. #       Related Task #

10                            T1

21                            T2

20                            T3

Step 2: Sequencing in Ascending Order:

Seq. #       Related Task #

10                            T1

20                            T3

21                            T2

Step 3: Re-numbering in multiples of 5:

Seq. #          Related Task #

50                            T1

100                          T3

105                          T2