Restricting 'Off Wing' tasks in packages: You can assign tasks with job type ‘Off Wing’ to a package, if the process parameter ‘Allow Off Wing Jobs?' under entity type ‘Package Type’ and entity User-Defined Packages or Log Cards in the Define Process Entities activity in Common Master is 1/Yes for the package type. However, the system does not allow for 'Off Wing' tasks in a package, if ‘Allow Off Wing Jobs?' is 0/No.
The system sets Need Date of the material request on the basis of the AME Ref. # referenced task as illustrated in the table
If Plan Start Date of the task/discrepancy is a |
Need Date of the MR will be set as |
Current/Future date |
Plan Start Date of the task/discrepancy |
Past date |
System Current date |
In a situation in which multiple material requests are auto-generated by the system, the requests are consolidated on the basis of Need Date or the serviceable request warehouse of the task work center.