Example:
SWO for engine: SWO-1
Tasks for the SWO: T1 and T2
Plan Start / End date for SWO1: 17-Jun 2011 to 22-Jun 2011
Plan Start date for the task T1: 20-Jun 2011
Backdated reporting Time Limit
(in days): 5 More..
The system does not allow modification to this field:
If the “Start date / Time” is modified as 15-Jun 2011.
If the “End date / Time” is modified as 30-Jun-2011.