Entering resource details for a standard procedure

What you can do in this page

Unified Glossary

Basics of using a typical web page

Using Online Help

This option allows you to add or modify the details of resources required for executing the   standard procedure. Tell me more

The “Edit Resource Requirements” page appears.

The system displays the following in the “Standard Procedure Details” group box:

SP Applicability

 

Indicates whether the standard procedure is applicable for “Aircraft”, “Engine” or “Component”.

Base Aircraft Model #

The number identifying the base aircraft model on which the standard procedure can be performed

Std. Procedure #

The standard procedure selected in the main page, for which the resource details have to be specified.

Std. Procedure Description

The textual description of the standard procedure.

Zoom facility available

Resource Type

Use the drop-down list box to select the type of the resource for which the details are to be added or modified. The available options are “Tools”, “Others”, “Skills”, and “Equipment”. The system sets the field to “Skills” by default.

Resource #

The resource required for completing the standard procedure (Alphanumeric, 40). The resource of type “Skills” must have been defined in the "Create Employee File" activity of the "Employee Information" business component and resource of type “Tools”, “Others” and “Equipment” must have been defined in the “Work Center” business component. For each resource type, the resource number must be unique within the multiline.

 

Help facility available.

The system fills in the following field on clicking the “Edit Resource Requirements” pushbutton:

Resource Description

The textual description of the resource.

Time Unit

Use the drop-down list box to specify the unit of measurement for the resource time, which could be  “Minutes”, “Hours” or “Days”.

Est. Time

The number of hours, minutes or days the resource is required to complete the standard procedure (Decimal). Mandatory. For “skill” type resources, if the sum of estimated duration, in terms of hours, is greater than the total man-hours estimated for the standard procedure, the system automatically sets the estimated man-hours to the sum of the estimated duration entered in the multiline

Est. Nos

The number of resources required for completing the standard procedure (Integer). Ensure that the value entered in this field is positive.

Approval Reqd.?

Use the drop-down list box to indicate whether the resource should be an approved resource or not. The available options are Yes” and “No” and the system displays “No” by default.

Sign-Off?

Use the drop-down list box to indicate whether the user has to sign after the standard procedure has been carried out by the resource. The available options are “Yes” and “No”. This field is applicable only for “skill” type resources.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Entering resource details for a standard procedure– An overview

Edit Standard Procedure -  A summary of the activity

This option allows you to add or modify the details of resources required for executing the standard procedure. If you wish to define the resources for the standard procedure, you can enter details such as resource code, estimated duration, and number of resources needed against each resource type. You can also indicate whether the resource should be an approved resource or not and whether sign off is required for the “Skill” type resource. Based on this information during work reporting sign off sheet will be automatically generated by the system. You can also retrieve resources that have already been defined for the standard procedure and modify its details. The system updates the resource details and sets the last modified date to the current server date.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

What you can do in this page

Select resource type required for access panel task

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Select resource type required for access panel task

You can specify the resource required for completing the standard procedure.