Authorizing budget requirement details

What you can do in this page

Glossary

Basics of using a typical web page

Using Online Help

This page allows you to authorize the selected budget requirement. You can authorize a budget requirement that is in the “Fresh” status. This page also allows you to modify the details of the budget requirement if required before the authorization. The status of the budget requirement after authorization is updated as “Active”. This budget requirement cannot be modified any longer.

This page also allows you to return the selected budget requirement. You can return the budget requirement that is in the “Fresh” status. A budget requirement is returned to the user who has created it for modification. This budget requirement can be authorized after modifications. The system stores the login ID of the user and the system date along with the modified details.

The “Authorize Budget Requirement” page appears.

The system displays the following:

Requirement No

A unique number identifying the budget requirement.

Status

The status of the budget requirement. It must be “Fresh”.

 
  • Fresh – indicates a newly created budget requirement that can be modified or authorized

Request Date

The date on which the budget requirement is created (Date Format). Mandatory.  This date must be a valid one for the selected financial year. This date must not be after the system date.

The system displays the following:

Finance Book

The code identifying the finance book for which the budget requirement has been created.

Financial Year

The financial year for which the budget requirement has been created.

Asset Class Code

Use the drop-down list box to select the code identifying the asset class for which the budget requirement is being raised. The “Asset Class” must have been defined in the “Create Asset Class” activity of the “Asset Type Definition” business component and must be in “Active” status. All the asset classes that have been defined for the company will be available for selection in the ascending order.

The system displays the following:

Asset Description

The textual description of the selected asset class.

Amount Required

The amount required as budget (Decimal). Mandatory. This amount must be greater than zero.

 

Press <Enter> key.

 

The system calculates and displays the budget amount in the base currency of the company in the “Base Amount” field.

Currency

Use the drop-down list box to select the code identifying the currency in which the budget requirement must be created. The “Currency” must have been defined in the “Create Currency and Country” activity of the “Organization Setup” business component. All the currencies mapped to the login organization unit are available for selection in the ascending order.

Exchange Rate

The exchange rate of the currency in which the budget requirement is being created, if the currency is different from the base currency of the organization unit (Decimal, Mandatory). The exchange rate must be greater than zero. The exchange rate must be a value, which falls within the exchange rate tolerance set in the “Exchange Rate” business component. The system displays ‘1’ by default on launch of the page if the currency is the base currency.

 

Press <Enter> key.

 

The system calculates and displays the budget amount in the base currency of the company in the “Base Amount” field.

Note: This field must not be left blank if a value exists in the “Amount Required” field.

The system displays the following:

Base Amount

The amount required as budget in the base currency of the company. This value is calculated and displayed as the product of the amount required and the exchange rate.

Remarks

Any comments pertaining to the creation of the budget requirement (Alphanumeric, 255).

The modifications made to the budget requirement are saved. The system updates the status of the budget requirement as “Active”.

The system updates the login ID of the user to the “Last Modified By” field and the system date to the “Last Modified Date” field.

The system updates the status of the budget requirement as “Returned”.

The system updates the login ID of the user to the “Last Modified By” field and the system date to the “Last Modified Date” field.

The system displays the following:

Created By

The login ID of the user who has created the budget requirement.

Created Date

The date on which the budget requirement was created.

Last Modified By

The login ID of the user who has last modified the budget requirement.

Last Modified Date

The date on which the budget requirement was last modified.

To proceed, carry out the following:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

What you can do in this page

Modify and authorize budget requirement

Return budget requirement

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Modify and authorize budget requirement

You can modify the details of the budget requirement before the authorization. The system stores the modification details when the budget requirement is authorized.

The system saves the modifications made to the budget requirement. The status of the budget requirement is updated as “Active”. This budget requirement cannot be modified any longer.

Return budget requirement

You can return the budget requirement to the user who has created it. A budget requirement that is returned can be modified and authorized at a later stage. You can return budget requirements that are in the “Fresh” status.

The status of the budget requirement is updated as “Returned”. This budget requirement can be retrieved for authorization after it has been modified.