Amending budget details

Glossary

Basics of using a typical web page

Using Online Help

This page allows you to amend the details of a budget. You can amend a budget that has been authorized and is in the “Active” status. You amend details like the amount allocated as budget, the percentage and amount that have been set as variance. You can also remove the type of variance that has been set for the asset class. The system generates a unique number identifying every amendment made. The login ID of the user and the system date is stored along with the amended details.

The “Amend Budget” page appears.

The system displays the following:

Budget No

A unique number identifying the budget.

Amendment No

A unique number identifying the amendment that has been made to the budget.

Status

The status of the budget. It must be “Active”.

 
  • Active – indicates that the budget has been authorized.

Budget Date

The date on which the budget has been allocated.

Financial Year

The financial year for which the budget has been created.

Total Base

 

Requirement Amount

The total budget requirement amount in the base currency of the company.

Total Allocated Amount

The total amount allocated as budget.

Total Base Utilized Amount

The total amount for which proposals have been created in ‘’active’’ status for the asset class till date.

Total Base Variance Amount

The total amount till which the actual amount can vary from the budget. This amount is in the base currency of the company.

Total Base Balance Amount

The balance budget amount that is yet to be used. This amount is also in the base currency of the company.

The system displays the following in the “Budget Information” multiline:

Finance Book

The code identifying the finance book for which the budget has been allocated.

Asset Class Code

Use the drop-down list box to select the code identifying the asset class for which the budget is being allocated. The “Asset Class” must have been defined in the “Create Asset Class” activity of the “Asset Type Definition” business component and must be in “Active” status. All the asset classes that have been defined for the company will be available for selection.

 The system displays the following in the “Budget Information” multiline:

Asset Class Description

The textual description of the asset class.

Amount Required

The amount that has been defined as the budget requirement for the asset class.

Currency

The currency in which the budget requirement amount has been entered.

Exchange Rate

The exchange rate of the currency in which the budget requirement has been entered. This exchange rate will be defined if the currency is different from the base currency of the company. It both the currencies are the same, “1” is displayed by default.

Base Amount

The budget requirement amount in the base currency of the company.

Allocated Amount

The amount that has been allocated as budget for the asset class (Decimal). Mandatory.

Allow Variance

Use the drop-down list box to set whether you would allow a variance in the budget amount that has been allocated. You can select from “Yes”, “No” and “Unlimited”.

 
  • Yes – indicates that a variance of the budget will be permitted till the percentage or the amount specified.

 
  • No – indicates that there must be no variance in the amount allocated as the budget.

 
  • Unlimited – indicates that there could be an unlimited variance in the amount budgeted and the expenditure incurred.

Variance %

The percentage the actual amount can vary from the budget (Integer). This field must not be left blank if there is no value entered in the “Variance Amount” field.

Note: This field must be left blank if “No” or “Unlimited” has been selected in the “Allow Variance” field.

Variance Amount

A flat amount till which the actual amount can vary from the budget (Decimal).

Note: This field must not be left blank if there is no value entered in the “Variance %” field.

The system displays the following:

Base Allocated Amount

The amount allocated as budget in the base currency of the company.

Base Variance Amount

The amount that could be the budget variance in the base currency of the company.

Amount Utilized

The total amount for which proposals have been created in ‘’active’’ status for the asset class till date.

Base Utilized Amount

 The total amount for which proposals have been created in ‘’active’’ status for the asset class till date.

Balance Amount

The allocated budget amount that is not yet used.

Base Balance Amount

The allocated budget amount that is not yet used in the base currency of the company.

Remarks

Any comments on the reason for the budget allocated with reference to the required amount (Alphanumeric, 255).

The system calculates and displays the total budget requirement amount, amount allocated as budget and the variance amount in the base currency of the company.

The modifications made to the budget are saved. The system generates an amendment number for the budget.

The system updates the login ID of the user to the “Last Modified By” field and the system date to the “Last Modified Date” field.

The system displays the following:

Created By

The login ID of the user who has allocated the budget.

Created Date

The date on which the budget was allocated.

Last Modified By

The login ID of the user who has last modified the budget.

Last Modified Date

The date on which the budget was last modified.

To proceed, carry out the following:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

What you can do in this page

Set Budget Variance

Calculate the allocated amount

Amend Budget

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Set Budget Variance

You can set whether there can be a variance in the budget that has been allocated.

Calculate the allocated amount

You can calculate the sum total of the budget amounts that have been allocated. You can also calculate the sum total of the requirement amount and the variance amount.

The system calculates and displays the “Base Allocated Amount”, “Base Variance Amount”, “Total Base Requirement Amount”, “Total Base Allocated Amount” and the “Total Base Variance Amount”.

Amend Budget

You can amend the details of the budget if required during the amendment process.

A unique amendment number is generated for the amendment made to the budget.