Viewing assignment details for the resource

Unified Glossary

Basics of using a typical web page

Using Online Help

This page allows you to view the loading details of the selected resource. Resource loading . Tell me more.

The “View Resource Loading” page appears.

The system displays the following:

Date Format

The format in which the date and time fields are displayed in this page. This format is displayed from the "User Preferences" business component based on the login user ID. In case the format is not defined, the system displays the date and time format from the “Enterprise Modeling” business component by default.

The system displays the following in the “Resource Details” group box:

Resource #

The resource for which the loading details are displayed.

Resource Description

The textual description of the resource.

Zoom facility available.

Resource Type

The type of the resource, which could be “Equipment”, “Skills”, “Tools” or “Others”.

Reference Date

The starting date from which you wish to view the loading details for the resource (Date Format).

The system retrieves in the multiline, the work centers to which the resource is associated and the utilization of resource as a percentage for each day starting from the date entered in the “Reference Date” field.

The system displays the following fields in the “Loading Details in %” multiline:

Work Center #

The work center to which the resource is associated.

Day 1 … Day 15

The percentage of utilization of the resource on each day starting from the date specified in the “Reference Date” field. The loading is calculated as follows:

  • The number of hours for which the resource is available in the day, which is assumed to be 24 hours, for resource types other than “Skill”. For “Skill” type of resources, this value is retrieved from the “HR Setup” business component.

  • The total number of hours for which the resource is actually assigned to the work center is retrieved from the “Assign Work Order / Task(s)” page in the “Assign Resource To Work Order(s)” activity.

The loading is then calculated using the following formula:

Resource Loading = (Assigned hours of the resource * 100) / (Available Hours of the resource * Productivity factor).

Note: Productivity factor is the number that indicates the efficiency of the resource that is specified in the “Associate Work Center Attributes” activity of the “Work Center” business component. The productivity factor is assumed as ‘1’ if it is not already specified for the resource.

Work Center Description

The textual description of the work center.

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Viewing assignment details for the resource – An overview

This page allows you to view the loading details of the selected resource. Resource loading refers to the utilization of the resource in a day during the execution of the WO task or the work order. The loading is specified in percentage and calculated as follows:

Resource Loading

 =

(Assigned hours of the resource*100)

/

(Available hours of the resource * Productivity Factor)

 

Note: Productivity factor is the number that indicates the efficiency of the resource that is specified in the “Associate Work Center Attributes” activity of the “Work Center” business component. The productivity factor is assumed as ‘1’ if it is not already specified.

In this page, the resource loading details are calculated with respect to the work center to which the resource is assigned. You can enter the reference date from which the loading details must be viewed.

Note: You can view the details only for 15 days at a time.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

What you can do in this page

View resource loading

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

View resource loading

The utilization of the resource in a day during the execution of the work order or task can be viewed.