Viewing resource actuals information for maintenance report

View Technical Log - A summary of the activity

Glossary

Basics of using a typical web page

Using Online Help

In this page, you can view the resource actuals reported against a maintenance report. You can specify the maintenance report for which you need to view the resource actuals. The system displays the resource actuals, such as the resource code, type, description, actual hours for which the resource is utilized for the selected maintenance report.

The “View Resource Consumption” page appears.

The system displays the following:

Date & Time Format

The format in which the date and time  fields are displayed. This format is displayed from the "User Preferences" business component based on the login user ID. In case the format is not defined, the system displays the date format from the “Enterprise Modeling” business component by default.

The system displays the following in the “Tech Log Details” group box:

Execution Ref #

The execution reference number for which you need view the resource information.

The system displays the package type before the execution reference number.

Status

The status of the execution reference.

Log  #

The number identifying the log , which contains the execution reference details.

Aircraft Reg #

The aircraft registration number to which the execution reference is associated.

Display Option

Use the drop-down list box to specify the display option of the resource consumption. The combo is loaded with “Estimation” and “Actuals”. The system displays “Estimation” on page launch.

Note: If the Display Option is selected as “Estimation”, then the system retrieves the estimated resources for the corresponding Execution Ref # at each task level. Only Estimated hours will be fetched and Actual hours will be blank. If the Display Option is selected as “Actuals”, then the system retrieves the actual resources for the corresponding Execution Ref # at each task level. Both Est. hours and Actual hours will be fetched.

The system displays the following in the “Resource Consumption Details” multiline:

Task #

The number identifying the task.

Seq #

The number identifying the sequence.

Resource #

The number identifying the resource for which you need to view the resource information.

Resource Type

The type of the resource, which could be “Equipment“, “Tools” or “Others”.

From Date

The date starting from which the resource is utilized for the maintenance report.

From Time

The time from which the resource is utilized for the maintenance report.

To Date

The date until which the resource is utilized for the maintenance report.

To Time

The time until which the resource is utilized for the maintenance report.

Est. Hours

The estimated time spent in hours on the maintenance report.

Actual Hours

The actual time spent in hours on the maintenance report.

Resource Description

The textual description for the resource.

Task Description

The description of the task.