Select options for exporting the visit package details into project management software

Unified Glossary

Basics of using a typical web page

Using Online Help

This page allows you to select the options to export the visit package to the project management software.  Tell me more

The “Select Export Option” page appears.

The system displays the following field:

Date Format

The format in which the date fields are displayed in this page. This format is displayed from the "User Preferences" business component based on the login user ID. In case the format is not defined, the system displays the date format from the “Enterprise Modeling” business component by default.

The system displays the following in the “Visit Package Details” group box:

Visit Package #

The number identifying the visit package.

Title

The description of the visit package.

Zoom facility available.

Planned Start Date

The date on which the visit package execution has to be started.

Activity

Select this option to export the activities to the project Management software.

Resource Pool

Select this option to export the resource pool to the project Management software.

Calendar

Select this option to export the calendar to the project Management software.

Relationships

Select this option to export the relationships to the project Management software.

Note: Ensure that you select at least one of the export options.

Click here to learn more details about the transfer to Project Management Software.

Top

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Select options for exporting the visit package details into project management software - An Overview

This page allows you to select the details to be exported to the project management software. You can set the options as  “Activity”, “Resource Pool”, “Calendar” or “Relationships”. The system exports the selected information, as found in the “Visit Package” business component, to the project management software installed in the system. You can later import the required details from the project management software, into your system.

Note: When the PMT is launched for the first time, it automatically creates the Project ID for the given set of information and updates all the project related details such as resource pool, calendar, activity list and relationships, along with the timestamp. For subsequent updates, you can set the option to export a particular group of details.

 

Top

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Transfer to Project Management Tool

A Project Management Tool (PMT) uses sophisticated algorithms and powerful graphical displays to analyze interdependencies between activities, build network and identify and resolve resource bottlenecks, if any. The Aviation solution interfaces with these project management software tools to plan, monitor and control the execution aspects of complex jobs effectively.

In this activity, you can export the visit package details. It plans the scheduled start date and end date automatically for the work units included in the visit package. You can also import the visit package contents from the project management software.

You can export the details into PMT for the following purposes:

Scheduling Tool

The use of the PMT as a complete scheduling tool will require bi-directional flow of information. It represents the most comprehensive form of interfacing, all entities that are required for planning and resource leveling are exported to the projects software, including the activities (and its key attributes), resource pool, calendar information and the relationships between the activities. The revised activity details and relationship details are updated back into the work application database.

For scheduling the visit package, prior to release

For exporting the data, the details required by a PMT are categorized as Activity, Resource, Resource Pool, Calendar and Relationships. The grouped information is exported to PMT.

Export Option: Activity

The visit package details are exported to the PMT in the following sequence:

The standard procedures will be broken down into individual task constituents.

All the tasks belonging to the Visit Package are transferred to PMT. The information in the MSP (Microsoft Project) is sequenced based on the WBS (Work Break Down Structure) levels specified, that is, Primary Work Center forms the first level, Work center at the second level and the tasks to be performed in the work center are at the third level.

Along with the elapsed time, the time unit is also updated and it is concatenated as day, hour etc.

If the priority description corresponds to numbers between 1 and 9 in the application, then the priority is set as follows:

1 - Highest

2 - Very high

3 - Higher

4 - High

5 - Medium

6 - Low

7 - Lower

8 - Very low

9 - Lowest.

If the priority number is greater than 9, then the system assigns the least priority.

The following details are imported from the PMT:

Note: The newly added work units and also those work units, which are in “Released”, “Deferred” and “Pending Deferral” status, will not be imported.

Export Option: Resource Pool:

The resource pool details are exported to the PMT in the following sequence:

If the "Work Center Hierarchy Check" option is set as 'Yes' in the “Set Options” activity, then the exported resource must have been mapped either to the primary center or to its child work centers.

If the “Work Center Hierarchy Check" option is set as 'No' in the “Set Options” activity, then the resource must have been mapped to the work center of the login organizational unit.

For the resources of type “Skills” defined in the “HR Setup” business component, the total number of resources mapped to the exported work center is passed as ’Available units’ for the primary skill specified.

For the resources other than “Skills”, the total quantity mapped to the exported work center is passed.

The rate information defined in “HR Setup” business component is passed for the resource.

If the details are not available from the “HR Set Up” business component, then the resource quantity, primary skill and rate are exported from the “Work Center” business component.

Export Option: Resource:

The resource details are exported to the PMT:

The resource requirements at the visit package level are retrieved along with the resource requirements at the task level. The visit package level resource requirements have to be equally distributed among the tasks of the work order.

Along with the elapsed time, the time unit is also updated and it is concatenated as day, hour etc.

Assign units is calculated as follows:

(Reqd. Time of the Resource / Tot. Est. Time of the work unit) * No. of resources

Export Option: Calendar:

The following information is exported to the PMT:

If the integration between “Work Center” and “Time Management Scheduling” exists, the rota schedule mapped to the primary work center is exported as “Project Calendar” and it will span the duration of 3 weeks prior to the project start date and 3 weeks after the planned end date.

If the integration does not exist, the default calendar is considered by the PMT.

Export Option: Relationships:

The following details are exported to the PMT:

The following details are imported from the PMT:

The lag is split into Value and Time Unit.

Graphical View

The PMT is utilized purely for its ability to render information in graphical form (through usage of Gantt charts, resource usage graphs etc.). An interface of this type requires only unidirectional information flow; however, the interface might still require all activity details and allied information (resource pool, calendars etc.), to be made available in the project management software.

Complex business functions such as reviewing the progress of the visit package that handles large volumes of data across a time line, will utilize this type of interface.

For viewing the progress of the visit package

To view the progress of the visit package, the grouped information is exported into PMT.

Export Option: Activity:

The visit package details are exported to the PMT in the following sequence:

The standard procedures will be broken down into individual task constituents.

All the tasks belonging to the Visit Package are transferred to the PMT. The information in the Microsoft Project (MSP) is sequenced based on the WBS (Work Break Down Structure) levels specified; That is, Primary Work Center forms the first level, Work center at the second level and the tasks at the third level.

If the priority description corresponds to numbers between 1 and 9 in the application, then the priority will be set as follows:

1 - Highest

2 - Very high

3 - Higher

4 - High

5 - Medium

6 - Low

7 - Lower

8 - Very low

9 - Lowest

If the priority number is greater than 9, then the least priority is assigned.

If no work is reported against a task then the “Planned Start Date” and “Planned End Date“ are exported into MSP. If reporting has started against a task, then the “Actual Start Date” will be exported.

Export Option: Resource Pool:

The resource pool details are exported to the PMT in the following sequence:

If the "Work Center Hierarchy Check" option is set as 'Yes' in the “Set Options” activity, then the exported resource must have been mapped either to the primary center or to its child work centers.

If the “Work Center Hierarchy Check" option is set as 'No' in the “Set Options” activity, then the resource must have been mapped to the work center of the login organizational unit.

For the resources of type “Skills” defined in the “HR Setup” business component, the total number of resources mapped to the exported work center is passed as the ‘available units’ for the primary skill specified.

For the resources other than “Skills”, the total quantity mapped to the exported work center is passed.

The rate information defined in “HR Setup” business component is passed for the resource.

If the rate information is not available, then the resource quantity, primary skill and rate are exported from the “Work Center” business component.

Export Option: Resource Requirements:

The following resource requirement details are exported to the PMT:

The resource requirements at the visit package level are retrieved along with the resource requirements at the task level. The visit package level resource requirements have to be equally distributed among the tasks of the work order.

Along with the elapsed time, the time unit is also updated and it is concatenated as day, hour etc.

Assign units is calculated as follows:

(Reqd. Time of the Resource / Tot. Est. Time of the work unit) * No. of resources.

Export Option: Calendar

The following information is exported to the PMT:

If the integration between “Work Center” and “Time Management Scheduling” exists, then the rota schedule mapped to the primary work center is exported as Project Calendar and it will span the duration of 3 weeks prior to the project start date and 3 weeks after the planned end date.

If the integration does not exist, then the default calendar is considered by the PMT.

Export Option: Relationships:

The following details are exported to the PMT:

The time unit is concatenated with the lag.